Create a Change Event from an Observation

Back Current Lesson - 5/29 Next

Creating a change event allows you to prepare for the cost of a change before it becomes an actual cost. For example, if a project manager is anticipating the need to change the paint colors of a project, he or she can start preparing for that cost by creating a change event, which describes the estimated financial cost of the change, as well as which cost codes will be affected. After creating a change event, they can then create an RFQ (Request for Quote), which is sent to the appropriate subcontractors for pricing. When RFQs are created and responded to by the assigned subcontractors, change orders can then be created based upon the submitted quote.

  1. Navigate to your project's Observations tool.
  2. Locate the observation that you will use to create the change event. Then click View.
  3. Click + Create Change Event.
    Note: The system redirects you to the create page in the Change Events tool.
  4. Complete the steps documented in Create a Change Event
  5. Click Save