The "Copy & Paste" function can be a timesaver for takeoffs; it works exceptionally well with windows and railings.
Be sure to utilize the different "Quantity" functions for takeoffs; i.e., use flooring for "Qty. 1" and perimeter for "Qty. 2" to figure the amount of base. You can also use "area counts" to calculate the number of openings/windows.
These are the expected generic takeoffs:
Foundation (to help with the calculation for the below-grade waterproofing)
CMU
Exterior glazing (Count/ Perimeter for WP/ SF) using one condition.
Stucco (SF stucco plus LF of foam trim)
Exterior metal panels/ grilles
Balcony railing
Stair railings (if the section is available, that is fine; if not, per Flight)
Misc. Metals
Roof Area
Roof Walking Pad
Waterproofing:
Below Grade.
Un-covered basement area
Window openings.
Eyebrow.
Balconies.
Amenity Level (elevated)
Pool surface area (elevated)
Planters (elevated)
Doors
Flooring
Elevators
Pool
Plumbing
Pavers
Site analysis
Site elevations: FFE, existing grade, water table, top of pile cap, and bottom of elevator pit.
Indicate import or export. (Provide approximate quantity)
Auger Cast Piles (count by type, total LF if possible)
Structural excavation for pile caps.
Why do we perform takeoffs?
To compare quantities with subcontractors and ensure they have a complete scope.
To calculate the cost of a specific trade.
To calculate a scope item that a subcontractor is missing.
Takeoff Scale
The most crucial step in a takeoff is to set the scale of each drawing accordingly. With the wrong scale, your takeoff will be completely wrong.
Check the scale on the drawing using an extended dimension.
If the scale is missing or incorrect on the drawing, adjust it with a known dimension on the drawing. Use a long dimension to change.
Takeoff Comparison with Subcontractors
Kast typically does not send out takeoffs to the subcontractor, nor are they included in the scope sheets. Standard practice is to get subcontractors on the phone and compare takeoffs verbally.
When checking a subcontractor's quantities, ask if they include waste. Typically, we don't consider waste when comparing takeoffs with subcontractors.
CMU
Quantify the amount of SF of CMU.
Takeoff approach
Option 1 (preferred)
Use Architectural floor plans and do the linear takeoff. Include openings.
Calculate the area of the wall by multiplying the length by floor height.
Deduct SF of openings. (Please note that subs do not deduct openings)
Option 2
Use elevations and include openings. Do area takeoff
Use floor plans and do linear takeoff to account for any walls not represented on elevations. Calculate the area of the wall by multiplying the linear foot of the wall times the wall height
Deduct SF of openings.
Account for the following items:
Roof parapet walls
Balconies enclosed by CMU and not by railing
Any CMU partitions/enclosures at roof or amenity decks
Site walls
Dumpster enclosures
Decorative columns between site fencing
Decorative columns at building facades and balconies
Crash walls in the garage
To calculate # of Block:
# Blocks = SF of CMU * 1.125
Exterior and Interior Glazing
Quantify the amount of SF for exterior and interior glazing
Divide takeoff into the following:
Exterior glazing by type (ex, window type A, window type B, storefront type K)
Interior glazing by type (ex, type CC, door lites)
Takeoff approach
Option 1 (Preferred)
Use floor plans to do linear takeoff windows.
Calculate the area of glazing by multiplying the length of the window by the glazing height.
Option 2
Use elevations. Do area takeoff for types of windows.
Use floor plans and do linear takeoff to account for any exterior and interior glazing not represented on elevations. Calculate the area of glazing by multiplying the length by the glazing height.
Option 3
Use floor plans. Do count takeoff for types of windows.
Use the window schedule for dimensions and calculate the area of each window type. Calculate the area of glazing by multiplying the count of window types by the glazing area.
Miscellaneous glazing that should be taken off separately:
Interior fire-rated glazing
Door lights (typically supplied by glass sub and installed by door sub)
Stucco
Quantify the amount of SF for exterior and interior stucco.
Takeoff approach
Option 1 (Preferred)
Use floor plans and do the linear takeoff. Include openings.
Calculate the area of the wall by multiplying the length of the wall by the floor height.
Deduct SF of openings
Option 2
Use elevations and include openings. Do area takeoff
Use floor plans and do linear takeoff to account for any walls not represented on elevations. Calculate the area of a wall by multiplying the length of the wall by the floor height.
Deduct SF of openings.
Use floor plans and do the linear takeoff. Include openings.
Calculate the area of the wall by multiplying the length of the wall by the floor height.
Deduct SF of openings
Account for the following items:
Top and inside of roof parapet walls
Top and inside of any balcony enclosed by CMU and not by railing
Balcony divider/return walls
Balcony ceilings
Other stucco ceilings (interior or exterior)
Stairwells (if required by bid documents)
Parking garage interior walls (if required by bid documents)
Planter exterior walls, top, and interior to dirt line
Site walls, dumpster enclosure
Check wall type schedule for any interior walls with stucco
Do linear take–off of foam trim using elevations or floor plans.
Stairwell railing
Quantify the amount of LF of railing/ or Flight of no section was provided
Divide takeoff into the following:
Guardrail
Grabrail
Takeoff approach
Use stair elevation for diagonal railing up the stairs. Do linear foot takeoff.
Use floor plan for railing landing areas. Do linear foot takeoff
Exterior Metal Panels
Quantify the amount of SF for exterior metal panels. (Will be used for waterproofing, too)
Divide takeoff into types of metal panels:
For example, perforated panels, grilles, flat panels, etc.
Takeoff approach
Use elevations. Do area takeoff.
Aluminum or Glass Railings
Quantify the amount of LF for railings
Divide takeoff into the following:
Unit balcony railings
Aluminum railing
Glass railings
Common area railings
Aluminum railings
Glass railings
Takeoff approach
Use floor plans and do linear takeoff railings.
Miscellaneous Metals
Quantify counts for the following items:
Parking garage bollards
Exterior bollards
Parking garage corner guards
Parking garage pipe protectors
Elevator separator beams – as the elevator company
Elevator hoist beams
Pit ladder
Elevator sump pit grate
Takeoff approach
Use floor plans and do a count takeoff.
Roofing
Quantify the amount of SF for roofing
Divide takeoff into the following:
Flat roofs
Sloped roof systems (ex, metal standing seam, roof tiles)
Metal coping cap LF
Walking pad LF
Takeoff approach
Use floor plans to do area takeoff of roofing.
Account for sloping on tiled roofs and metal standing seam roofs.
Do a linear takeoff metal parapet cap.
Do a linear takeoff for walking pads.
Account for the following items
Omit upturns.
Consider upturns only if the upturn goes all the way to the parapet.
Top of elevator shafts.
Stairwell tops.
Other structures have a roof above the main roof.
Check all floor plans and account for any roofing areas located below the main roof.
Waterproofing
Quantify SF of waterproofing
Divide takeoff by location and type (if possible) of waterproofing:
Exterior walls elevator pits – typically bentonite waterproofing
Elevator pit foundation, pile caps, mat foundations – typically bentonite waterproofing
Interior of elevator pit wall and slab – typically fluid applied or sheet
Elevated exposed decks – typically hot-applied or cold-applied system
Elevated pool and spa structural box – typically hot-applied or cold-applied system
Planter tops, walls, and slabs are typically cold and applied to walls and slabs. Sometimes, slab calls for hot-applied
Balconies—typically a fluid-applied traffic coating, but it can also be a sealer. The painting sub can quote the sealer.
Interstitial spaces – typically fluid applied
Exterior openings - typically fluid-applied or cementitious
Parking garage slabs over occupied space – typically vehicular traffic coatings
Exterior metal panels – typically fluid applied
Back of house rooms – typically fluid applied
Concrete eyebrows – typically fluid applied
Check for waterproofing for the following items if applicable to the project:
Top of parapet typically if no metal coping is shown
Exterior walls or site walls below grade
Shower floors and curbs (units and common areas) DIV09
Tub decks- DIV09
Shower benches- DIV09
Bathroom floors for common areas- DIV09
Unit AC/WH closets- DIV09
Walls of hydrostatic slabs
Takeoff approach
Use floor plans and elevations as convenient to do area takeoffs
Doors
Quantify counts of leaves (counts) or counts of openings.
Single door = one leaf
Double door = two leafs
Pocket door = one leaf
One bi-fold partition = two leafs
Divide takeoff into the following:
Units doors
Entrance doors
Interior swing doors
Pocket doors
Bi-fold doors
Common Areas
Wood doors
Hollow metal doors
Takeoff approach
Use floor plans and count takeoff.
Flooring
Quantify the amount of SF for flooring
Divide takeoff into the following:
Units
Types of flooring and location (if possible) = ex: carpet, tile, vinyl plank, wood, etc
Bathroom wall tile
Bathroom shower floor
Kitchen backsplash (if applicable)
Common areas
Type of flooring
Bathroom wall tile
Other wall tiles
Account for the following items
Check if unit AC/WH closets require flooring
Check for any flooring at unit balconies
Don't back out of cabinets.
Elevators
Quantify the number of stops and number of openings per elevator
Takeoff approach
Use floor plans to count the takeoff of stops and openings.
Organize takeoff per floor.
Account for rear opening doors.
Example of takeoff:
Pools
Quantify the amount of SF for pools and spas.
Takeoff approach
Use floor plans and do area takeoff.
Include concrete entrance steps.
Omit perimeter coping
Plumbing
Quantify the number of bathrooms, bathtubs, and showers.
Takeoff approach
Use floor plans to count the takeoff of tubs and showers
Organize takeoff per unit type
Example of takeoff:
Pavers
Quantify the amount of SF for pavers.
Divide takeoff into the following:
Location of paver:
Sidewalks,
Roadway/streets
Pedestrian road crosswalks
Pool deck
Elevated terraces
All elevated pavers to be mud set (must)
All pavers above the basement to be mud set (must)
Etc
Takeoff approach
Use floor plans to do area takeoff.
The pool sub typically includes pool perimeter coping.
Do linear takeoff of any concrete headers butting pavers.
Auger Cast Piles
Quantify the count of piles per size and type
Divide takeoff into the following:
Compression piles
Tension piles – more expensive than compression
Piles are the actual concrete round support penetrating the ground. Please do not confuse it with a pile cap. The pile cap is the concrete box above the piles.
Takeoff approach
Use floor plans and count takeoff.
It is always good to check the length of the pile with the subcontractor. The subcontractor might have the correct number of piles but the incorrect length.
The volume of Pile Caps – DIV03
Quantify the amount of volume for pile caps.
Divide takeoff into the following:
Type of pile cap, ex: 3PC, 4PC, 30 PC, etc
Takeoff approach
Quantify the count of each type of pile cap.
Identify the depth of each pile cap.
Quantify the surface area of each type of pile cap.
Pile Cap Volume for each type = surface area times depth
Structural Excavation-
This topic will be an individual training topic since it involves parameters that are defined by the Team during the logistic process.
The purpose is to calculate the cubic yards of dirt for the structural excavation.
Sitework Fill or Export
This topic will be an individual training topic since it involves parameters that are defined by the Team during the logistic process.
The purpose is to calculate the cubic yards of dirt needed to fill the site or cubic yards of dirt to export the site.