VDC File Storage Policy
DO NOT STORE FILES SOLELY ON YOUR LOCAL DRIVE, WORKING FILES OR OTHERWISE!
Overview
- Save all work-related files to folders within the KAST Egnyte file structure under the Y-Drive
- All project-specific files should be within the project folder structure, either Precon/Projects or Ops
- The Egnyte Private folder is reserved for “personal”, non-project-specific, files only (vacation request, expense reports, etc.)
- Do not download files from Egnyte to your local hard drive, but instead utilize the Egnyte Desktop app to sync working files as needed, and de-sync when finished with that project, pursuit, or assignment.
Best practice is to utilize the Egnyte Desktop App for accessing and storing files
- The one caveat is that larger, model, files should be saved to your secondary (D) drive & this app does not support secondary drives
- However, ALL folders and files that you have access to on Egnyte are available here provided you have internet access
- Best practice is not to rely on internet access connection for large files
- KAST-specific instructions on how to use Egnyte here
- Examples of folders to "sync" using this tool
- 00.VDC Pursuits\_Case Studies
- 00.VDC Pursuits\_Marketing
- 00.VDC
In order to sync files to your secondary (typically D) hard drive you will need to download the Egnyte Desktop App
- Examples of folders to "sync" using this tool
- 00.VDC Pursuits\[PROJECT YOU ARE WORKING ON]
- [PROJECT YOU ARE WORKING ON]\400.BIM & CAD
- Precon/Projects/[PROJECT YOU ARE WORKING ON]/[ESTIMATE STAGE]/VDC
- "Estimate Stage" may be GMP, RFP, DD, etc. Choose the most current
Process for "Pursuits"
- If Precon has established a Folder Structure in Y:\Shared\Precon\Projects
- use the VDC folder under that structure
- If Precon does not yet have their own folder set up:
- Navigate to the 00.VDC Pursuits folder on your Y-Drive (Egnyte Desktop App)
- Y:\Shared\00.VDC Pursuits
- Right click [PROJECT NAME] folder and select "copy"
- Right-click in the empty white space of the folder and select "paste"
- Rename [PROJECT NAME] to the name of the project
- Open the Egnyte Sync settings in your task bar (down by the clock)
- Choose the options to select folders to sync
- Add the new folder to the list by checking the box
- Navigate to the 00.VDC Pursuits folder on your Y-Drive (Egnyte Desktop App)
Standards for Operations Phase
- ALL work on a project must be saved within that project folder, typically somewhere in the 400.BIM folder, once the Operations phase has begun.
- Operations phase, broadly, is defined by working on coordination, mockups, or 3D logistics for the on-site team.
- Within a project, the "Staff" folders are to be avoided.
- Exceptions would be early startup when you're working on the Coord Plan and Schedule
- If you've started coordination, the plan and schedule should already be complete and saved in
- 400.BIM & CAD\410.BIM Docs\411.Coord Plan
- Maintain and update the plan and schedule as you move through coordination.
- e.g. Sub misses 2 meetings and/or hasn't submitted a model in 2 weeks? That will likely have an impact on the schedule, so update the schedule accordingly and notify the project team.
- When notifying the team, be BRIEF. They don't care about the details of the ceiling or the whatever.
- X sub has not turned in a model in Y weeks and it's causing a Z delay to the coordination schedule. This is/is not currently impacting the critical path of the construction schedule
- e.g., is it pushing your signoff date past the drop dead date on the calculated Coordination Schedule)
- X sub has not turned in a model in Y weeks and it's causing a Z delay to the coordination schedule. This is/is not currently impacting the critical path of the construction schedule
- When notifying the team, be BRIEF. They don't care about the details of the ceiling or the whatever.
- e.g. Sub misses 2 meetings and/or hasn't submitted a model in 2 weeks? That will likely have an impact on the schedule, so update the schedule accordingly and notify the project team.
- 2D Drawings Produced from BIM for the field should be saved to
- Y:\Shared\000.Project Template\200.Field\210.Coord & Markups\211.BIM