Update Activity Progress
Background
Updating progress is essential for keeping the project team informed of site productivity. In Procore, the Status of a task is a dynamic calculation. The system compares the Percent Complete you enter against the current date and the scheduled finish date to determine if a task is "In Progress," "Late," or "Completed".
Things to Consider
-
Required User Permissions: 'Standard' level permissions or higher on the project's Scheduling tool.
-
Master vs. Look-Ahead: In Option 1 (Read-Only), you should perform progress updates within the Look Ahead tab to provide the most granular field data.
Steps
Method 1: Update via the Gantt Chart (Graphical)
-
Navigate to the project's Scheduling tool.
-
Locate the taskbar on the Gantt chart.
-
Click and drag the white arrow at the bottom of the taskbar to the right.
-
Note: The shaded area within the bar will increase to visually represent the work finished.
-
Method 2: Update via the Task Table
-
Locate the % Complete column in the schedule table.
-
Click into the cell for the desired task.
-
Type the numerical percentage (e.g., "50") and press ENTER.
Method 3: Update via Task Details
-
Double-click the colored taskbar on the Gantt chart to open the Task Details side panel.
-
Enter the value in the % Complete field.
-
Click Save.