Distribute a Snapshot of a Project 360 Report
- Last updated
- Save as PDF
Objective
To distribute a snapshot of a 360 report.
Things to Consider
- Required User Permissions:
- For company reports: the user is a company admin.
- For project reports: the user has 'Standard' or higher level permissions on the 360 Reporting tool and the report was created by you.
Steps
Distribute a Report
To distribute a 360 report created using the 360 Reporting tool, follow the steps below:
-
Navigate to the 360 Reporting tool.
- Use the company 360 Reporting tool for company reports.
- Use the project 360 Reporting tool for project reports.
- Navigate into the 360 Report created in the 360 Reporting tool.
- Click the vertical ellipsis (⋮) and select Distribute.
- In the Recipients field, search for and select the users or distribution groups that you would like to email the report to.
- In the Send As drop-down menu, select PDF or Excel.
- Click Distribute.
Schedule a Distribution
To schedule a distribution for a 360 report, follow the steps below:
-
Navigate to the 360 Reporting tool.
- Use the company 360 Reporting tool for company reports.
- Use the project 360 Reporting tool for project reports.
- Locate the report created in the 360 Reporting tool.
- Click the vertical ellipsis (⋮) and select Distribute.
- In the Recipients field, search for and select the users or distribution groups that you would like to email the report to.
- In the Send As drop-down menu, select PDF or Excel.
- Select one of the following options from the Frequency drop-down menu:
- Daily
- Daily (Weekdays Only)
- Weekly
- Monthly
- Select the options in the Settings section to schedule when the report will be distributed based on your Frequency selection.
- Click Create.