Finalize an Inter Project Materials Transfer
Background
To move materials to a new project, create an inter project materials transfer.
Once the inter project transfer finalized, Procore automatically creates a shipment for the receiving project. When the receiving project finalizes a receipt with the associated shipment, the transfer status is updated to 'Transfer Complete' or 'Transfer Received' in the relevant project.
Things to Consider
-
A transfer must be submitted before it can be finalized.
-
After you finalize a transfer and the status is 'Final', you can only edit the following fields:
-
Attach files
-
Custom Fields
-
Notes
-
-
'Quantity Available' counts are updated when the transfer is finalized and the status is 'Final'.
-
Quantities of Pre-Transfer 'Acceptable' materials that were transferred from your project are removed from the 'Quantity Available' in your inventory.
-
Quantities of 'Unacceptable' and 'Damaged' Materials are already excluded from the 'Quantity Available' in your inventory.
-
Steps
-
Navigate to the project's Materials tool.
-
Click the Inter Project Transfers tab.
-
Click the inter project transfer number.
-
Click Finish Review.
-
Select Move back to Draft if there changes that need to be made to the receipt.
-
Select Mark as Final to finalize the receipt.
-