Background

To move materials to a new project, create an inter project materials transfer.

Once the inter project transfer finalized, Procore automatically creates a shipment for the receiving project. When the receiving project finalizes a receipt with the associated shipment, the transfer status is updated to 'Transfer Complete' or 'Transfer Received' in the relevant project.

Things to Consider

Steps

  1. Navigate to the project's Materials tool.

  2. Click the Inter Project Transfers tab.

  3. Click the inter project transfer number to view the details.