Create Materials Requirements
Background
Note
The process for importing materials and creating material requirements is the same.When managing your materials, you can import a list of the required materials to the Materials tool.
After you import your materials, a requirements document is automatically created for the scope of that work. After its finalized, required inventory quantities are updated, and you can create shipments and receipts to track orders placed outside of Procore.
To update an existing requirements document, upload a new version with the existing document's name in the 'Materials Requirements Document Name' column. The Requirements document will be updated to match your latest upload.
'Closing' a requirements document indicates that the scope of work is complete. The Materials tool automatically removes those 'Required' quantities from your inventory to ensure your stock levels accurately reflect the current and remaining needs of the project.
Things to Consider
-
The 'Quantity' in your imported file automatically updates the 'Quantity Required' field in the Inventory tab.
-
If the same materials are added with a different Unit of Measure (UOM), it will create a separate line item.
-
You can import a maximum of 20,000 rows per import.
-
Most errors cause the entire import to fail, requiring you to fix the errors and import again. However, if a document is in a 'Final' state, only items for that specific requirements document will fail, while the rest will import.
-
Inventory quantities are updated when a requirements document is finalized.
-
Creating a New Requirements Document
-
A new requirements document will be created when the 'Material Requirement Document Name' is unique.
-
-
Updating a Requirements Document
-
To update an existing requirements document, ensure the 'Material Requirement Document Name' for your new upload exactly matches the original.
-
All line items and required 'Quantities' are updated to match the new upload.
-
If line items are removed from the upload:
-
The items will be deleted from the Requirements document.
-
The items stay in your inventory, but the removed quantities are deducted from the 'Required Quantities' column.
-
-
Prepare Materials for Import
-
Navigate to the project's Materials tool.
-
Click the Requirements tab.
-
Click the Import.
-
Click Download Excel Template.
-
Open the template in your spreadsheet software.
-
-
Save the file.
Import Materials
-
Navigate to the project's Materials tool.
-
Click the Requirements tab.
-
Click Import.
-
Attach the file.
-
Click Attach Files and select the prepared Materials import template. Then click Open.
-
Drag and drop the prepared Materials import template from your desktop to the 'Drag and Drop' section.
-
-
Click Upload.
Review and Submit Requirements
-
Navigate to the project's Materials tool.
-
Click the Requirements tab.
-
Click the 'Draft' requirements document you imported.
-
Review the requirements document.
-