Manage Change Orders on Commitment Invoices
Background
You can now manually select which change orders to include on your invoices. While previous versions added these items automatically or through a bulk Add function, this update gives more granular control over change orders on invoices by allowing you to manually review and select which items to add or remove .
Things to Consider
-
Required User Permissions:
-
Admin' level permissions on the project's Commitment Invoicing tool.
-
-
When creating a new invoice, any change orders that were previously approved or are currently pending-billable will be included automatically.
-
The system automatically adds Approved or Billable change orders to your next invoice.
-
You can manually add a change order:
-
if it is Approved or Billable.
-
if it has been updated after the invoice was created.
-
if it has not been included on a previous invoice in the same commitment.
-
-
You cannot delete change orders that were carried forward from a previous invoice.
-
To remove change orders, you must first move Approved or Paid invoices back to Draft status.
Prerequisites
-
Create a Commitment Invoice.
-
Make sure the commitment has available change orders (COs).
-
The change orders must be in an Approved or Billable status.
-
You must have an existing invoice created in the Commitment Invoicing tool.
Steps
Add Change Orders to an Invoice
-
Navigate to the project's Commitment Invoicing tool.
-
Click Edit next to the commitment.
-
Click the Invoices tab.
-
Click View next to the invoice.
-
Click Review & Add Change Orders.
-
Select the specific change orders you want to add, or check 'all' to add them at once.
-
Click Add.
Note: A banner confirms you added the change orders.
Remove Change Orders from an Invoice
-
Navigate to the project's Commitment Invoicing tool.
-
Click the Invoices tab.
-
Click Edit next to the invoice.
-
Locate the change order you want to remove.
-
Click Delete.
Note:
-
You can only remove change orders in Edit mode.
-
The icon to delete Change Orders is only visible when grouping includes Commitment Change Orders.
Remove a Newly Added Change Order
-
In the Change Orders section of the draft invoice, locate the item you want to remove.
-
Uncheck the change order.
-
Click Save to update the invoice totals.
Note: Deleting a change order returns it to the Review and Add Change Orders list for future use.