Objective

To change the date to enter information for a previous log entry.

Things to Consider

  • Required User Permission: 'Standard' or Admin' on the project's Daily Log tool.

Steps

  1. Navigate to the project's Daily Log tool.
  2. Click on the calendar icon next to today's date to pull up a monthly view.

    dl-date2015-05-27_14-20-11.png
  3. Select a past date.
  4. Enter information into the desired log(s).
  5. Click Add.

 