Objective

To delete a purchase order or subcontract from a project's Commitments tool.

Background

When you delete a purchase order or subcontract using the steps below, Procore permanently moves it to the Recycle Bin. 

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Commitments tool.
  • Additional Information:
    • If the Delete button is grayed out and unavailable, check to see if the status is set to 'Approved'.  You must change the status before it can be deleted. 
    • Deleted purchase orders and subcontracts are moved to the Recycle Bin and cannot be retrieved. 
  • For companies using the icon-erp-synced2.png ERP Integrations tool: Show/Hide  

Prerequisites

Steps

  1. Navigate to the project's Commitments tool.
  2. Beta Under the Contracts tab, locate the purchase order or subcontract. Then click View.
  3. Click Delete.
     Warning
    • If the button is grayed out and unavailable, check to see if the status is set to 'Approved'.
    • Procore does NOT permit you to delete 'Approved' purchase orders or subcontracts. You must change the status before it can be deleted. 
    • When you delete a purchase order or subcontract, Procore permanently moves it to the Recycle Bin.
    • Purchase orders and subcontracts cannot be retrieved from the Recycle Bin at a later time. 
  4. Click OK on the confirmation window.
    The system moves the deleted purchase orders or subcontracts to the Recycle Bin.

 