Budget & Forecast Snapshots: User Guide
- Last updated
- Save as PDF
Table of Contents
- Overview
- Considerations
- Key Features
- Manage Access
- For a Project
- For the Company
- More
Overview
This guide introduces Budget & Forecast Snapshots, powerful features for tracking, analyzing, and reporting budgeting and forecasting changes in Procore Financial Management. With the Project level Budget tool, snapshots capture budget and forecasting views at specific times, creating valuable historical records to show how project finances evolve. Use them for official monthly reporting or create ad-hoc snapshots for a clear view of your financial path.
This table details the difference between project status snapshots and ad-hoc snapshots.
| Feature | Project Status Snapshots | Ad Hoc Snapshots |
|---|---|---|
| Intended Use | Official reporting, formal budget reviews, and a centralized company-wide financial history. | Immediate insights, focused project analysis, and a project-level budgeting and forecasting history. |
| Data Capture | Standardized, formal monthly/quarterly captures for consistent company-wide analysis. | Quick, flexible captures tailored for individual and project team needs. |
| Comparison Focus | Analyze trends and variances across projects for formal reporting. | Capture specific data points to address unique project requirements. |
| Historical Reference | Centralized, company-wide record for auditability and long-term analysis. | Project-level budgeting and forecasting history within the project for internal tracking. |
| Impact on Formal Company Reporting | Directly contributes to the official company-wide financial historical data. | Remains within the project, without affecting official company-wide records. |
| Location | Accessible in the Company-level Project Status Snapshot tool and the Budget tools' Project Status Snapshots tab. | Accessible within the snapshots feature the Project level Budget tool and omitted from official project status snapshot records. |
| Export Options | CSV or PDF | CSV or PDF |
| Forecasting Integration | Not Available | Available |
Considerations
Some key considerations when using the Budget & Forecast Snapshots feature include:
Things to Consider
-
Project Status Snapshots are visible to all Budget tool users with 'Read Only' level permissions or higher.
-
The Company level Project Status Snapshots tool allows viewing Project Status Snapshots across all projects (see View Snapshots in the Project Status Snapshots Tool for details and permissions). This company-level tool does not have an 'Admin' permission level; its permissions are limited to None, Read Only, and Standard.
-
The comparison tool is designed to aggregate and compare numerical values that can be summed, such as dollar amounts. Consequently, certain types of columns are excluded from the comparison view:
-
Percentage-Based Columns: These are not included because adding percentages together can lead to inaccurate totals. A true total percentage must be recalculated from the sum of the source data, a function not yet supported.
-
Text-Based Columns: Columns containing non-numeric data, such as 'Budget Notes' or 'Description', cannot be mathematically aggregated and are therefore excluded.
-
Quantity-Based Columns: Columns like 'Production Quantity' are omitted to prevent calculation errors. The system cannot aggregate quantities that may have different units of measure (e.g., adding linear feet to cubic yards).
-
Key Features
These are the key features:
Create Ad Hoc or Project Status Snapshots
The Create Snapshot window in the Project level Budget tool contains these options to create snapshots. To learn more about snapshots, see Create a Snapshot from the Budget Tool.
Important
It's essential to note that once your company enables this feature, all previous snapshots in your Procore project(s) will be automatically classified as ad-hoc.View Historical Project Status Snapshots
The Project Status Snapshots tab in the Budget tool allows your team to view all project snapshots in one place. This includes the snapshot's name, a description (if entered), and its status in your workflow. The table also includes a date and time stamp showing when it was created and the creator's user name.
Manage the Review Workflow for Project Status Snapshots
For teams with a formal process for reviewing project status snapshots, users can conveniently click the drop-down menus in the Status column to indicate the snapshot's status. This is helpful for teams who review snapshots regularly (i.e., weekly, monthly, and so on). Users can change the status of a snapshot line item in the Project Status Snapshots tab in the Project level Budget tool or with the Company level Project Status Snapshots tool.
Configure Columns
Users can click Configure to choose which columns to show and hide. Once configured to show, users can drag-and-drop the table's columns to any location in the table. For example, if users want to see whether a budget line item is over or under its projected value, move the Projected over Under column to the left side of the table. If users want to see the estimated cost of the budget line item at completion, move the Estimated Cost at Completion column to the left.
Users can configure the columns to show/hide in the Project Status Snapshots tab in the Budget tool or with the new Company-level Project Status Snapshots tool.
Create and Manage Custom Statuses for Project Status Snapshots (Beta)
In Beta
Custom statuses for project status snapshots are available for the Budget and Project Status Snapshots tools. To enable this feature for all projects and users in your company account, join the Create Custom Statuses For Project Status Snapshots beta program through Procore Explore.Users can create and manage custom statuses for project status snapshots to align project tracking with internal procedures. This feature provides greater flexibility by moving beyond standard "Under Review" and "Approved" options. It enables tailored processes that match your organization’s specific budget review stages. See Create a Custom Status for Project Status Snapshots.
-
Tailored Tracking: Create up to 50 color-coded custom statuses in the Company level Admin tool for quick visual identification.
-
Status Mapping: Link custom statuses to standard color-coded status types, such as Open (Grey), Pending (Yellow), Closed (Green), and Void (Red) in the Company level Admin tool to maintain data integrity across your budget.
-
Default Status: Set a custom status as the default status for new project status snapshots in the Company level Admin tool to standardize reporting across all projects.
-
Status Application: Apply custom statuses to project status snapshots in the Project Level Budget tool and the Company level Project Status Snapshots tool so that your budget management workflows reflect your organization's requirements for forecasting and reporting.
-
Granular Visibility: Use the Company level Project Status Snapshots tool to filter project status snapshots by custom statuses, providing deeper insight into project health across your portfolio.
Analyze Budget Variance Between Project Status Snapshots
To analyze budget variance, click the Variance icon in the data table's column headers. This expands the selected column group to show the line item's current value, previous value, and variance. This eliminates the need to calculate variance in third-party spreadsheets.
Export Project Status Snapshots
Users can click Export to download the list snapshots in the Project Snapshots tab to a Comma Separated Values (CSV) file format for offline access.
Monitor and Review Snapshots Across Projects
The Company level Project Status Snapshots tool transforms how your teams monitor and review snapshots by consolidating all of your project's status snapshots in a single location. Access to the tool is controlled by the company permission templates that an administrator configures for your team. This lets your team save valuable time by eliminating the need to distribute project snapshots by alternate means, such as email. Users also no longer need to post PDF copies and manage copies in an outside information silo.
Manage Company Level Access Permissions with Permission Templates
Company-level permission templates are the best way to control who can create or view snapshots with the Company level Project Status Snapshots tool. An administrator can then manage access based on user roles and responsibilities.
Control Access to the Company Level Project Status Snapshots Tool
In a company permissions template's Financial Management section, the default permission setting is None. You can only configure access to Read Only or Standard; Admin level permissions are unavailable for the Project Status Snapshots tool.
Adjusting Permission Settings:
-
To allow users to view all project status snapshots, choose 'Read Only' level permissions.
-
To allow users to change the status of a project status snapshot or export a snapshot list, choose 'Standard'
level permissions.
Manage Access
Company and project permission templates are the best way to control who can create or view snapshots. An administrator can then manage access based on user roles and responsibilities.
Things to Consider
- Required User Permissions:
- To manage company and project permission templates, 'Admin' level permissions on the Company level Permissions tool.
Manage Access to Project Status Snapshots at the Company Level
An administrator controls access to the Company level Project Status Snapshots tool using company permissions templates. See these steps:
Example
In a company permissions template's Financial Management section, the default permission setting is None. You can only configure access to Read Only or Standard; Admin level permissions are unavailable for the Project Status Snapshots tool.

Adjusting Permission Settings:
- To allow users to view all project status snapshots, choose 'Read Only' level permissions.
- To allow users to change the status of a project status snapshot or export a snapshot list, choose 'Standard' level permissions.
Manage Access to Snapshots at the Project Level
To see project status snapshots in specific Procore projects and their own ad hoc snapshots, users need access to the Budget tools within those projects. Users only see data for the projects they have permission to access. See these steps:
Example
This example shows the available permission levels for the Budget tool in the Financial Management section of a project permissions template. A template's default setting is None.

- Required User Permissions:
To provide users access to snapshots on the Project level Budget tool:- To view all project status snapshots within a project's Budget tool, assign 'Read Only' level permissions.
- To create project status snapshots using the project's Budget tool, assign 'Standard' or higher level permissions.
- To create their own ad-hoc snapshots using the project's Budget tool, assign 'Standard' or higher level permissions.
Create a Snapshot
Create a Snapshot from the Budget Tab
In Beta
Custom statuses for project status snapshots are available for the Budget and Project Status Snapshots tools. To enable this feature for all projects and users in your company account, join the Create Custom Statuses For Project Status Snapshots beta program through Procore Explore.123Users can create a Project Status Snapshot or an Ad Hoc Snapshot from the Budget tab. Only Project Status Snapshots are saved.
DID YOU KNOW?
You can now edit a snapshot's name, type, and description directly from the budget banner without needing to delete and recreate it. To learn more, see Edit a Budget Snapshot.-
Navigate to the project's Budget tool.
-
Click the Budget tab.
-
Click Create Snapshot.
This opens the Create Snapshot window.

-
Under Snapshot Type, choose an option:
-
Project status. Choose this option for official reporting, such as a monthly report that needs review.
-
Ad hoc. Choose this option for a simple snapshot.
-
-
Enter the snapshot information:
-
Name. Enter a name for the snapshot.
-
Status. Select a standard status (Under Review or Approved).
Select a custom status. For details on how to create a custom status, see Create a Custom Status for Project Status Snapshots. -
View. Select a budget view for the snapshot.
-
Description. Enter a description of the snapshot.
-
-
Click Create.
When complete, the Snapshot Created banner appears at the top of the page.

Create a Snapshot from the Forecasting Tab
Users can create an ad hoc snapshot from the Forecasting tab.
-
Navigate to the project's Budget tool.
-
Click the Forecasting tab.
-
Click Create Snapshot.
This opens the Create Snapshot window.
-
Enter the snapshot information:
-
Name. Enter a name for the snapshot.
-
View. Select a budget view for the snapshot.
-
Description. Enter a description of the snapshot.
-
-
Click Create.
When complete, the Snapshot Created banner appears at the top of the page.
View a Snapshot
There are different ways to view snapshots in the Budget tool.
View a Project Status Snapshot from the Project Status Snapshots Tab
Any user can view a project status snapshot tab from this tab. Ad-hoc snapshots are not saved and do not appear in this tab.
- Navigate to the Project level Budget tool.
- Click the Project Status Snapshots tab.
- In the Name column, click the snapshot to open.
- The system opens the snapshot in your web browser. A Viewing from Snapshot banner appears.

- Click the View Current Data button to return to your project's current budget data
View a Project Status Snapshot from the Project Status Snapshots Tab
Any user can view a project status snapshot tab from this tab. Ad-hoc snapshots are not saved and do not appear in this tab.
- Navigate to the Project level Budget tool.
- Click the Project Status Snapshots tab.
- In the Name column, click the snapshot to open.
- The system opens the snapshot in your web browser. A Viewing from Snapshot banner appears.

- Click the View Current Data button to return to your project's current budget data.
View a Project Status Snapshots as the Snapshot Creator
Snapshot creators can also view a snapshot immediately after it's created.
- Complete the steps in Create a Budget Snapshot.
When saved, the Snapshot Created banner displays.

- Click View Snapshot Data.
- The label on the banner changes to Viewing from Snapshot.
- Review the snapshot as needed.
- Click the View Current Data button to return to your project's current budget data.
View an Ad-Hoc Snapshot as the Snapshots Creator
Ad Hoc snapshots can only be viewed after creation. Only project status snapshots are saved.
- Complete the steps for an ad-hoc snapshot in Create a Budget Snapshot.
When saved, the Snapshot Created banner displays.

- Click View Snapshot Data.
- (Optional) See Export a Budget Snapshot if you want to save it.
Important
Ad-hoc snapshots aren't saved after the current session. You must export it if you want to see it later. - Click the View Current Data button to return to your project's current budget data.
Configure Columns
- Navigate to the Project level Budget tool.
- Click the Project Status Snapshots tab.
- Click Configure Columns.
This opens the Table Settings panel.

- Under Configure Columns, you have these choices for each available column:
- Show columns. Move the toggle switch to the right. The system's default setting is to show all available columns.
- Hide columns. Move the toggle switch to the left.
- When finished, click the Close (x) icon on the panel.
Apply a Budget View
Navigate to the project's Budget tool. Then click the Budget, Budget Details, or Project Snapshot Status tab and select an option from the View menu. To add views to this menu, see Assign a Budget View to a Project.

Note
-
Procore offers company accounts several standard budget views. See What are Procore's standard budget views?
-
Your company can create custom budget views or modify existing views. For details, see Set up a New Budget View.
View a Budget Snapshot
Navigate to the project's Budget tool. Then, click the Budget or Forecasting tab and select an option from the Snapshot menu. To add snapshots to this menu, see Create a Budget Snapshot.

Analyze Variance
Analyze Line Item Variance on the Budget Tab
In Beta
An enhanced budget table is available for analyzing line item variance between budget snapshots. See Analyze Line Item Variance Between Budget Snapshots (Beta).This action analyzes variance by comparing a snapshot with the active budget.
-
Navigate to the project's Budget tool.
-
Click the Budget tab and select a standard or custom budget view from the View menu.
-
Click Analyze Variance.
This opens the Select Comparison Columns to Analyze Variance window. -
From the Comparison Snapshot menu, select the snapshot to compare it with your budget data.
-
Under Columns to Display, choose one (1) option:
-
Comparison Column and Variance Column. Shows both values.
-
Comparison Column Only. Shows the value from the comparison snapshot.
-
Variance Column Only. Shows the variance between the comparison snapshot and active budget.
-
-
Under Comparison Columns, mark one or more checkboxes to select the columns to analyze for variance.

-
Click Save.
Procore analyzes the current budget and snapshot for variance.Example
This example shows the Comparison Column and Variance Column option using Estimated Cost at Completion as the comparison column. The blue column label shows the snapshot data. The column labeled Variance shows the difference between the snapshot and your budget.

Analyze Aggregate Variance Between Snapshots on the Project Status Snapshots Tab
This action analyzes the aggregate variance between two snapshots.
-
Navigate to the project's Budget tool.
-
Click the Project Status Snapshots tab and select a standard or custom budget view from the View menu.
-
Click the snapshot Name to open it.
-
On a column where it's available, click the Variance icon.
This expands the column to show the Current, Previous, and the Variance between the two snapshots.Example
This example shows the Current, Previous, and Variance columns that appear when you click the Variance icon on a column.

Export a Snapshot
- Navigate to the Budget tool.
- Click Budget or Forecasting tab.
- Create or view a snapshot.
Note
Ad Hoc and Project Status Snapshots are available for the Budget tab. Only Ad Hoc Snapshots are available for the Forecasting tab. - (Optional) Choose the budget view and apply any filtering or grouping options to the snapshot.
- Click Export.
Note
Because CSV is a flat file format, any applied grouping options are not included in exports to CSV. - Choose one of these options from the menu:
- CSV. This downloads a CSV file to the location configured in your web browser.
- PDF. This opens a PDF version of the file in a new browser window. To download it, use the options available in your web browser's PDF viewer.
Export a Snapshots List
- Navigate to the Project level Budget tool.
- Click the Project Status Snapshots tab.

- Modify the data table as needed. Your choices are:
- Select a standard budget view or one of your company's custom budget views from the View menu. See Set up a New Budget View.
- Click Configure Columns to show/hide columns from the display or to change the order of the column layout. See Configure Columns for the Project Status Snapshots Tab of the Budget Tool.
- Click Export and choose CSV from the menu.
This downloads a CSV file to the location configured in your web browser.
View Snapshots
-
Navigate to the Company level Project Status Snapshots tool.
-
Locate a snapshot in the list.
Note: If you want to view the snapshot, click the Open
icon in the Project column.Important
To see project status snapshots in specific Procore projects and their own ad hoc snapshots, grant users access to the Budget tools within those projects.

3. To filter the list view, click Filters.
This opens the Filters panel.

4. Set the available filters to focus on the snapshots you want to view. The filter options are:
-
Created By. Choose one or more snapshot creators.
-
Created On. Set a time frame using the calendar.
-
Project. Select specific projects to view their snapshots.
-
Region. Pick a project region.
-
Stage. Choose a project stage.
-
Status. Select a standard status (Under Review or Approved).
Select a custom status. For details on how to create a custom status, see Create a Custom Status for Project Status Snapshots. -
Office. Select an office.
-
Department. Pick a department.
-
Program. Select a program.
Configure Columns
- Navigate to the Company level Project Status Snapshots tool.
- Click Configure Columns.
This opens the Table Settings panel.

- Under Configure Columns, you have these choices for each available column:
- Show columns. Move the toggle switch to the right. The system's default setting is to show all available columns.
- Hide columns. Move the toggle switch to the left.
- When finished, click the Close (x) icon on the panel.
Apply Filters
- Navigate to the Company level Project Status Snapshots tool.
- Select a budget view from the View list.
- Click Filters.
This opens the Filters panel.

- Set the available filters to focus on the snapshots you want to view. Options are:
- Created By. Choose one or more snapshot creators.
- Created On. Set a time frame using the calendar.
- Project. Select specific projects to view their snapshots.
- Region. Pick a project region.
- Stage. Choose a project stage.
- Office. Select an office.
- Department. Pick a department.
- Program. Select a program.
Change Snapshot Status
In Beta
Custom statuses for project status snapshots are available for the Budget and Project Status Snapshots tools. To enable this feature for all projects and users in your company account, join the Create Custom Statuses For Project Status Snapshots beta program through Procore Explore.-
Navigate to the Company level Project Status Snapshots tool.
-
Locate the project status snapshot in the table.
-
Click the snapshot's Status cell and choose a standard status (Under Review or Approved).
Click the snapshot's Status cell and select a custom status. For details on how to create a custom status, see Create a Custom Status for Project Status Snapshots.

This updates the snapshot status at both the company and project levels.
Analyze Variance
Analyze Line Item Variance on the Budget Tab
In Beta
An enhanced budget table is available for analyzing line item variance between budget snapshots. See Analyze Line Item Variance Between Budget Snapshots (Beta).This action analyzes variance by comparing a snapshot with the active budget.
-
Navigate to the project's Budget tool.
-
Click the Budget tab and select a standard or custom budget view from the View menu.
-
Click Analyze Variance.
This opens the Select Comparison Columns to Analyze Variance window. -
From the Comparison Snapshot menu, select the snapshot to compare it with your budget data.
-
Under Columns to Display, choose one (1) option:
-
Comparison Column and Variance Column. Shows both values.
-
Comparison Column Only. Shows the value from the comparison snapshot.
-
Variance Column Only. Shows the variance between the comparison snapshot and active budget.
-
-
Under Comparison Columns, mark one or more checkboxes to select the columns to analyze for variance.

-
Click Save.
Procore analyzes the current budget and snapshot for variance.Example
This example shows the Comparison Column and Variance Column option using Estimated Cost at Completion as the comparison column. The blue column label shows the snapshot data. The column labeled Variance shows the difference between the snapshot and your budget.

Analyze Aggregate Variance Between Snapshots on the Project Status Snapshots Tab
This action analyzes the aggregate variance between two snapshots.
-
Navigate to the project's Budget tool.
-
Click the Project Status Snapshots tab and select a standard or custom budget view from the View menu.
-
Click the snapshot Name to open it.
-
On a column where it's available, click the Variance icon.
This expands the column to show the Current, Previous, and the Variance between the two snapshots.Example
This example shows the Current, Previous, and Variance columns that appear when you click the Variance icon on a column.

Export a Snapshots List
- Navigate to the Company level Project Status Snapshots tool.

- Click the Export menu and choose CSV.
This downloads a CSV file to the configured location for your web browser.
More
In Beta
This content is for participants in the Project Status Snapshots beta program. Learn how to join the beta in Manage Features With Procore Explore.Budget Tool
- About the Project Status Snapshots Tab (Beta)
- Analyze Variance Between Budget Snapshots (Beta)
- Apply the View, Snapshot, Group, and Filter Options on a Budget View
- Configure Columns for the Project Status Snapshots Tab of the Budget Tool (Beta)
- Create a Budget Snapshot
- Export a Snapshot List from the Project Status Snapshots Tab in the Budget Tool (Beta)
- Export a Snapshot from the Budget Tool (Beta)
Project Status Snapshots Tool
- Apply Filters to the Project Status Snapshots Tool (Beta)
- Change the Status of a Snapshot in the Project Status Snapshots Tool (Beta)
- Configure Columns for the Project Status Snapshots Tool (Beta)
- Export a Snapshot List from the Project Status Snapshots Tool (Beta)
- View Snapshots in the Project Status Snapshots Tool (Beta)