Split Resource Assignments
Objective
To split resource assignments in Resource Planning.
Background
Resources can work on multiple projects. If a project is delayed or a resource needs to temporarily move to a new assignment, you can split their current assignment. This allows you to adjust the dates for the remaining part of the assignment for the current project.
However, you can't move a split assignment to another project; you must create a new one.
Things to Consider
- Required User Permissions
- You cannot move split assignments to a new project.
Steps
- Navigate to the Company level Resource Planning tool.
- Click Assignments and select Gantt (Beta).
- Hover over the assignment bar and the date where you want to split.
- With your cursor over the date you want to split, right click the category bar and select Split.
- Drag and drop the assignment to new correct dates.
- Optional: Edit the Resource Assignment.
- Optional: Send Assignment Alerts.