Background

The Change History log tracks modifications made within Capital Planning, providing complete transparency and auditability for financial revisions.

Things to Consider

Required User Permissions:

  • 'Read Only', 'Standard', or 'Admin' level access to Capital Planning.

Steps

  1. Navigate to the Capital Planning tool.

  2. Locate the project or program item you wish to audit.

  3. Click the More Options (•••) icon adjacent to the line item or navigate to the item's details view.

  4. Select View Change History.

  5. Review the log for details on changed values, time stamps, and the user accounts responsible for each action.