Objective

To create a new project in Procore from an existing job in CMiC.

Background

A 'Job' in CMiC is equivalent to a 'Project' in Procore. If you first created a job in CMiC, you may use the steps below to add it to Procore. This creates a new Procore project that contains all of the relevant job information. Project data that is synchronized between the two systems include the following:

  • Project Cost Codes
  • Project Cost Types
  • Job Cost Data (See the 'Job Costs' subtab)

Important!  Each cost code must be assigned a category, otherwise you will receive an error message when you try to add the CMiC Job to Procore.

Things to Consider

  • Required User Permissions:
    • 'Standard' level permission on the ERP Integrations tool plus ONE of the following:
  • Limitations:
     Note
    If your company account has a project limit, a banner will appear at the top of the page to notify you when your project limit has been reached. 
  • Additional Information:
    • When importing a job from CMiC in order to create a new Procore project, you can select the project template that you want to apply to your new project in the 'Integration Settings' page for the ERP Integrations tool. See Configure Advanced Settings: ERP Integrations for CMiC. To learn more about project templates, see Configure a Project Template
    • It is recommended that you always perform the import before creating any commitments (i.e., subcontracts or purchase orders) in CMiC.

Steps

  1. Navigate to the company's ERP Integrations tool. 
  2. Click the Jobs subtab. 
  3. In the 'Filters' menu, click Ready to Import. 
    This reveals a list of all the unsynced jobs that exist in CMiC but have NOT be added as to your company's Procore account as projects. 

    filter-job-by-ready-to-import.png
     
  4. Review the Job information as follows:
    • CMiC ID. Ensure that the Job ID in CMiC is accurately reflected here. This will become the 'Project ID/Number' in Procore. 
    • Name. Ensure the Job Name in CMiC is accurately reflected here. This will correspond to the 'Project Title' in Procore. 
    • Procore Project Template. If you want to apply an existing project template to the new Procore project, select a template from the list. If you do not want to apply a template, choose 'Do Not Apply A Template....'. Note: The selections in this list are created in the Portfolio tool. See Configure a Project Template
  5. For each project line item, accept or reject the project:
    • To accept the job and import as a new Procore project, click Add to Procore
    • To archive the job and prevent it from being imported into Procore as a new project, click the icon-inspections-fail.png icon.