Refresh the Sage 100 Contractor® Cost Codes on a Project

Objective

To refresh the cost code list at the Project level to match the cost code list that's defined at the Company level. 

Background

If you (or someone at your company) updates the ERP Standard Cost Code list in the Company level Admin tool, you can use the steps below refresh those changes to a project's cost code list.

Example

Let's say your company's Procore account is configured to use the ERP Integrations tool with Sage 100 Contractor®. When you initially set up the ERP Integration, you and your Procore point of contact successfully synced the cost codes from your Sage 100 Contractor® system with the Sage 100 Contractor® Standard Cost Code list in Procore's Company level Admin tool. Since then, you've added your Company level Sage 100 Contractor® Standard Cost Code list in Procore to one or more Procore projects.

Now, your accounting team has recently added a new cost code to your 'Job' in Sage 100 Contractor®. After the new cost code in Sage 100 Contractor® is synced with the Sage 100 Contractor® Cost Code list in the Company level Admin tool, the next step is to refresh the list in the Admin tool to the list in your project's Admin tool. If you have multiple projects, you'll need to refresh each project's cost code list as described below.

Things to Consider

  • Required User Permission:
    • 'Admin' level permissions on the project's Admin tool
  • Prerequisites:
  • Supported Cost Code Delimiters:
    •  If your company has enabled the ERP Integrations tool for Sage 100 Contractor®, Procore permits the following cost code delimiters from Sage 100 Contractor®:  hyphen/dash (-).

Steps

  1. Navigate to the project's Admin tool. 
  2. Under Project Settings, click Work Breakdown Structure
  3. Under Segments, click Cost Code.
  4. Click Refresh Cost Codes.

    A GREEN banner appears to indicate that a refresh is in progress. When the banner disappears, the refresh is complete. 