Objective

To export a Prime Contract Change Order (PCCO) to Acumatica®.

Things to Consider

  • Required User Permissions:
    • 'Standard' or 'Admin' on the company's ERP Integrations tool.
      AND
    • The person's account must be granted the 'Can Push to Accounting' privilege in the Company Directory. See Grant Accounting Approver Privileges.
  • Prerequisites:
    • The ERP Integrations tool must be enabled on the company account.  
    • The ERP Integrations tool must be configured to work with Acumatica®. See Acumatica®: Setup Guide.
    • The Prime Contracts tool must be enabled on the project(s) that you want to sync. See Add and Remove Tools on a Project.
  • Requirements:
    • There must be a Prime Contract synced between the Procore Project and Acumatica®.
    • The Date field on a PCCO is required.
    • The PCCO must be in the 'Approved' status.
    • For each associated line item that you add to the change order's Schedule of Values (SOV), you may designate a unique associated Prime Contract line item or the same associated Prime Contract line item for all change order line items.
    • Vertical and Horizontal Markups are allowed. 
  • Considerations:
    • Each PCCO is exported to Acumatica® as a new project task.

Steps

Follow these steps to use the Acumatica® to export a PCCO created in Procore to Acumatica®:

  1. Create a PCCO using one of these methods:
  2. Send a PCCO to ERP Integrations for Accounting Acceptance
  3. Accept or Reject a PCCO for Export to Acumatica® 

See Also