Commissioning Sheets

Commissioning Sheets

 

  1. Copy the Commissioning Excel file from the Engineering\Commissioning folder into the applicable All Employees\Jobs\Commissioning folder.  

  2. Open the new commissioning spreadsheet.  

  3. Copy and delete sheets in the spreadsheet as necessary for the job based on scheduled equipment. Take care to ensure the most recent schedules are used. Each equipment tagged item gets its own sheet, except GRD which only gets one.  

  4. Print the spreadsheet as a Bluebeam pdf into the applicable All Employees\Jobs\Commissioning folder 

  5. In the Bluebeam pdf document, select Tools -> Form -> Automatically Create Form Fields. Press Esc.  

  6. Populate the fields based on the information available in the schedules and the equipment flyers as necessary. Installed Data, Actual Flows, Comments, etc. will be populated by installers.  

  

Notes: 

  1. Only one GRD sheet necessary. Extra copy only required if there are not enough lines available for the job.  

  2. Rooms on the GRD sheet should be called out using number first, then name i.e. "101 Hall" 

  3. Louvers, Vent Caps, Heat Exchangers, Air Separators, Hydraulic Separators, Thermostats, Plumbing Expansion Tanks, and RO Filters DO NOT need commissioning sheets.  

  4. Hydronic information located both on the Mechanical Schedules and on the Radiant/Snowmelt Plans.  

  5. RLA (Rated Load Amperage) is not often included in the design specs but it is testable so it is left in the commissioning sheets.  

  6. Manifold model numbers can be found in the vendor flyer based on number of circuits.  

  7. Take care to ensure most recent schedules are used. If a Construction folder exists within the job, the Installation Set is the best reference.  

  8. Bluebeam bogs down when there are an excessive number of pages. Saving the file to the desktop seems to help some but does not fully resolve the issue.