Objective

The BP IFC submittal is used to send bundled Barrier Post repair projects for construction.

 

Workflow

BP IFC submittal.jpg

Steps

1.   From the Project Tools dropdown, click the + beside Submittals.

1-click submitals +.jpg

 

 

2.   Complete the following fields:

  • Title - Enter the BP package name
  • Submittal Type - Select BP IFC
  • Responsible Contractor -  Select SDGE
  • Distribution List -  Enter the appropriate Gas Construction Supervisor 

2-choose BP  IFC.jpg

 

3.  Attach your files.

2.5-attach.jpg

 

 

4.  Scroll down to the Submittal Workflow and enter the appropriate District Supervisor(s), then click Create & Send Emails.

3-Dist Sup.jpg

 

 

5.  The completed form will all fields entered should look like below. Once all fields are completed, click the Create & Send Emails button and an email notification will go out to the District Supervisor and the Gas Construction Manager.