OKLAND TRAINING CENTER

oklandHorizontal_OSC.jpg

   

PROCUREMENT

Material Procurement at Okland is tracked on a custom-built Excel spreadsheet. This spreadsheet is linked to your P6 schedule and can backdate from date required to the work order needed date which prioritizes the procurement of subcontractors based on material review and lead times. This sheet should be completed by a senior project engineer (or above) and updated alongside the superintendent.

KEY FEATURES:
►Set up your required onsite date for all material procurement items.
►Prioritize items based on lead times and extended submittal review times.
►Update the log based on submittal status changes and confirmed order dates.