Meeting
|
Purpose
|
Scheduled By
|
Attendees
|
Recurrence & project Phase
|
|
Pre-Bid Review
|
A meeting held with the estimating team and the VP of Construction to discuss bid strategy and project specifics before submitting the bid.
|
Estimator
|
-
Estimator
-
BD
-
VP of Ops
-
President
|
|
|
Project Kick Off
|
The purpose of this meeting is to introduce the team, review the project requirements, and provide an update on the project's pre-construction status.
|
Estimator
|
|
|
|
Subcontractor Interview
|
Review the completeness of scope, inclusions and exclusions, price, financial health, past project references, and the ability to staff the project and maintain its schedule.
|
project manager
|
-
Project Manager
-
Superintendent
-
Project Engineer
-
Estimator
|
-
as needed
-
buyout & Project startup
|
|
Project Handoff
|
Meeting to review all project requirements and knowledge transfer from Preconstruction to Operations.
|
Project Manager
|
-
Project Manager
-
Superintendent
-
Project Engineer
-
Project Administrator
-
Accounting Clerk
-
VP of PC
-
VP of Ops
-
CFO/Controller
|
-
One Time
-
Project Start Up
|
|
Conditions of Mutual Satisfaction
|
The purpose of a Conditions of Mutual Satisfaction meeting is to encourage open communication among all parties involved in a project. This meeting ensures that everyone is on the same page and addresses any concerns before project start. Its main objectives are to maintain transparency, proactively tackle issues, and ensure that all participants stay committed to achieving the project's goals.
|
Project Manager
|
-
Project Manager
-
Project Engineer
-
Project Administrator
-
Superintendent
-
Project Director
-
Ownership Team
-
Design Team
|
-
One Time
-
Project Start Up
|
|
Pre-Construction Meeting
|
Coordination meeting between the Kier project team and all subcontractors before work commencing on the project.
All subcontractors are required to have site supervision and billing representation at this meeting. Come prepared to learn and discuss the project details and procedures where we will be reviewing Schedule, Quality Control, Contracts, Insurance Requirements, Change Orders, Procore Training and Billing.
|
Project Manager/Project Administrator
|
-
Project Manager
-
Project Engineer
-
Project Administrator
-
Superintendent
-
Project Director
-
Project Accountant
-
All Subcontractors
|
-
One Time
-
Project Start-up
|
|
Project Review
|
Review safety, schedule, risks, subcontractor issues, financials, and project management.
|
Project Administrator
|
|
|
|
OAC
|
Coordination meeting with the project team and ownership team to discuss any issues
|
Project Manager
|
-
Project Manager
-
Project Engineer
-
Superintendent
-
Ownership team
-
design team
|
|
|
Weekly Project Team Meeting
(Applicable with teams of 5+ members)
|
Coordination meeting with the project team to discuss any issues that need to be discussed in the OAC meeting or addressed immediately.
|
Project Manager
|
-
Project Manager
-
Project Engineer(S)
-
Superintendent(s)
-
Forman
|
|
|
Subcontractor Coordination & Safety Meeting
|
A Weekly coordination and safety meeting held by KIER Construction with subcontractors that are currently working on the job and will be working on the job within the next few weeks.
|
Superintendent
|
|
|
|
Safety Stand-Down
|
The stand-down meeting's purpose is to prioritize and reinforce KIER's commitment to our safety culture. It is dedicated to safety issues, incident reviews, and improvement discussions. Ultimately, the goal is to enhance safety awareness and reduce workplace incidents, fostering a safer environment for everyone.
|
Superintendent
|
|
|
|
Closeout Meeting
|
Meeting held to review the final budget, sub-performance, project successes, lessons learned, & owner satisfaction.
|
Project Administrator
|
-
Project Manager
-
Project Engineer
-
Project Administrator
-
Superintendent
-
Project Director
-
Accounting Clerk
|
|