VDC Action Plans
- Complete one Coordination Startup Action Plan at the beginning of every project
- Ideally when assigned
- At minimum prior to the MEPF subs being selected
- Prepare one Coordination Area Action Plan for each area on the Coordination Plan & Schedule
- Enter due dates based on Coord Schedule
- Initial models = 1 week prior to start of coord
- Final models = 1 week prior to Coord End
- Logs = Coord End
- Sign Off = Coord End + 1 week
- Enter due dates based on Coord Schedule