Sync CI Changes in Procore Clash Manager
Objective
To synchronize the changes in coordination issues between the Procore application and Navisworks®.
Background
Sync coordination issues to keep both Procore and Navisworks® up-to-date. The smoother workflow reduces errors and manual work. When both systems are updated, the responsible person is clear and accountable.
Things to Consider
- Required User Permissions:
- 'Admin' level permissions on the project's Coordination Issues tool.
Steps
- Click Sync CI Changes in Clash Manager.
- Review the changes.
- Select the coordination issues you want to sync.
- Click Sync Selected.