Skip to main content
Procore

Export the Labor Budget to Actual Report

Objective

To export the project's Labor Budget to Actual Report.

Things to Consider

  • Required User Permissions:
    • 'Read-only' level permission or higher on the project's Reports tool.
      AND
    • 'Read-only' level permission or higher on the project's Timesheets tool.
  • Prerequisites:
  • Supported Export File Formats:
    • Portable Document File (PDF)
    • Comma Separated Values (CSV)

Steps

  1. Navigate to the project's Reports tool.
  2. Scroll to the Project Reports section.
  3. Click Labor Budget to Actual.
  4. Click Export in the top right corner. 


     
  5. Select one of these options:
    • PDF: This exports a copy of the report to the PDF format. 
    • CSV: This exports a copy of the report to a comma-separated values file. 

 

  • Was this article helpful?