Bulk Edit Activities
Background
Managing large schedules often requires making the same update to several tasks at once, such as changing a duration or updating a resource. Using the Bulk Edit feature allows you to bypass individual entry, saving time and ensuring consistency across your project timeline.
Things to Consider
Required User Permissions: 'Standard' level permissions or higher on the project's Scheduling tool.
Steps
-
Navigate to the project's Scheduling tool.
-
Select the tasks you want to modify:
-
Click a task row.
-
Hold the CTRL (Windows) or CMD (Mac) key on your keyboard.
-
Click each additional task row you want to include in the edit.
-
Note: The selected rows will be highlighted.
-
-
Release the CTRL or CMD key.
-
Right-click anywhere on the highlighted area to open the options menu.
-
Click Bulk Edit.
-
Click into the cell you want to modify and enter the new value.
-
Press ENTER on your keyboard to apply the change to all selected tasks.
See Also
- Edit the Gantt Chart
- Manage Schedule Activity and Hierarchy
- Add Activities to a Schedule