Configure Your Project's Scheduling Path
Background
The first step in using the Scheduling tool is determining your "source of truth". Procore offers two primary workflows to suit your team's needs:
-
Option 1 (Read-Only): Ideal for complex projects where the master schedule logic is maintained in an external third-party tool. Procore acts as a collaborative window, allowing field teams to view data and create granular lookaheads without altering the master file.
-
Option 2 (Editable): Allows you to manage the schedule entirely within Procore. You can start with a blank slate or perform a one-time import to break ties with external software and leverage Procore's dynamic real-time logic updates.
Things to Consider
-
Required User Permissions: 'Admin' level permissions on the project's Scheduling tool.
-
Supported File Types: Procore currently supports Phoenix (.ppx), Microsoft Project (.mpp), and Primavera P6 (.xer).
Important
At this time, the latest cloud versions of P6 .xer files are not supported.
Steps
-
Navigate to the project's Scheduling tool.
-
Choose your scheduling path:
Option 1: Import a Read-Only Schedule
-
Ensure your master schedule is saved in a supported format (.mpp or .xer).
-
Click Attach Files to select the file from your computer or drag-and-drop the file into the Import Schedule panel.
-
Click Import.
-
Note: This data is grayed out by design to preserve the master logic.
-
Option 2: Create an Editable Schedule
-
Choose your starting method:
-
File Import (Option 2.1): Click Attach Files or drag-and-drop an existing schedule file. Future imports to this schedule will append new activity information rather than overwriting existing tasks.
-
Start from Scratch (Option 2.2): Set the Start Date, select a Default Calendar, and click Create.
-
-
Click Import (if uploading a file) or Create (if starting from scratch).
-
See Also
- Reset a Project Schedule
- Import a Project Schedule
- Scheduling: Create a Lookahead Schedule