Skip to main content
Procore

View the Change History of a Prime Contract

Objective

To view the change history for a Procore prime contract.

Background

The Change History tab summarizes the edits that have occurred on each prime contract created in the project's Prime Contracts tool.   

Things to Consider

  • Required User Permission:
    • 'Admin' permissions on the project's Prime Contracts tool.

Steps

  1. Navigate to the project's Prime Contracts tool.
  2. Locate the prime contract that you want to view in the list. Then click Edit
  3. Click the Change History tab.

    change-history-tab.png
     
  4. Review the contents of the Change History tab. Each line item corresponds to a change that was made and provides the following details:
    • Date. The date and time the change was performed. 
    • Action By.  The name of the user who performed the action. 
    • Changed. The prime contract information that was changed. 
    • From. The original value of the 'Changed' item in the prime contract. 
    • To. The updated value of the 'Changed' item in the prime contract. 

 

  • Was this article helpful?