Configure Assignments Gantt View
Objective
To configure your view for the Assignments Gantt.
Background
The Assignments Gantt allows you to view workforce requests, workforce assignments, and time off for a specific project or across all projects and people within your company. It also provides a multi-day view from one (1) day up to three (3) years.
Important
This tutorial is for the New Gantt Beta. For information for how to configure the legacy Gantt view, see View Assignments Gantt.Things to Consider
Steps
- Navigate to the Company level Workforce Planning tool.
- Click Assignments and select New Gantt.
- Take the following actions to configure your view:
Adjust Grid and Graph Ratio
- Hover over the divider that separates the grid and the graph.
- Click the divider and move it to the desired location using a drag-and-drop operation.
Group by Project or Resource
- Select to see information grouped by Resource or Project.
Configure Displayed Information
- Click the table settings icon.
- Move the toggle to the ON position or OFF position to show or hide details in the Gantt bars for the following:
- Project Information
- Allocation Information
- Time Off Information
- Hide Weekends
- Assignment Totals
- Then select to show People, Hours, Cost, or Man Days. See the Term Definitions for Totals to learn more about these metrics.
- Click and move the slider using a drag-and-drop operation to adjust the size for the following settings:
- Row height in the Gantt
- Task Border Radius
Expand and Collapse Projects, Categories, and Subcategories
- Next to the project, category, or subcategory, take one of the following actions:
- Click the expand icon to expand the information
- Click the collapse icon to collapse the information
Tip
To expand and collapse all projects, click the expand or collapse icon next to 'Project Name'.Zoom In and Out
- Click the zoom in icon or zoom out icon to view the Gantt from a single day, up to many years.