Below are the notable changes to the Integration by Procore which connects Procore to Viewpoint® Spectrum® in 2019.

Recent Changes 

New Unlink Button for Commitments Synced with Viewpoint® Spectrum® (2/5/2019) 

When a commitment in a Procore project is synced with a integrated ERP system, a link is created between the records stored in each system. Sometimes, users will inadvertently export a commitment from Procore and then discover that the commitment's data as exported was incorrect. When this occurs, the records in both systems will need to be deleted manually and then the correct information must be re-entered in Procore and exported to the integrated ERP system. See Unlink Commitments Synced with Viewpoint® Spectrum®.

New Change Order Date Field for CCO Exports (1/31/2019) 

Procore has added new Change Order Date field for Commitment Change Orders (CCOs). It can now be used by accounting approvers when exporting CCOs to Viewpoint® Spectrum®. See ERP Integrations: New Change Order Date Field for CCO Exports to Viewpoint® Spectrum®.

Admins Can Now Archive Standard Cost Codes on ERP-Integrated Projects (1/8/2019)   

Updated the Company level Admin tool to give Procore Administrators with the ability to archive Standard Cost Codes in Procore in order to prevent project users from adding those codes to a project. The archive action does not remove Standard Cost Codes from all lists.This update only affects users that have setup the ERP Integrations tool for Procore.