Resend a Rejected Project to ERP for Accounting Acceptance
Objective
To resend a previously rejected Procore project to the ERP Integrations tool to be accepted for export to your integrated ERP system by an accounting approver.
Background
If you previously sent a Procore project the ERP Integrations tool and it was rejected by your company's designated accounting approver, the accountant will typically include a reason when performing the rejection. The rejected project is then removed from the ERP Integrations tool. After correcting the issue(s), use the steps below to re-send the project to the ERP Integrations tool for acceptance by the accounting approver. After acceptance, the system will export the project to the integrated ERP system.
Important
Each ERP integration provides different directions of data flow between Procore and the ERP system. Some integrations may not allow you to add a Procore project to the ERP system. Instead, they will require you to add a project from your ERP system to Procore. To learn more about how your ERP integration works, see Things to Know about your ERP Integration.Things to Consider
- Required User Permissions:
- 'Admin' level permission on the Project level Admin tool.
- Prerequisites:
- Prerequisites and limitations may vary depending on the ERP system your account is integrated with. To learn more, see Things to Know about your ERP Integration.
Steps
- Navigate to the project's Admin tool.
- Under Project Settings, click General.
- Click Resend to ERP.