Export a PCCO as an OCO to CMiC
Objective
To export a Prime Contract Change Order (PCCO) as an Owner Change Order (OCO) to CMiC.
Background 
During a construction project, you will often create prime contract change orders. When a PCCO is created in Procore, you might need to export it as an OCO to CMiC. Follow the steps below to export a Procore PCCO as an OCO to CMiC.
Things to Consider 
- Required User Permissions:
    
- To enable the ‘Create Owner Change Orders’ setting, 'Admin' level permissions on the project's Admin tool.
 - To submit a request to enable the feature in your company's Procore account, you must be your company's Procore Administrator or the CMiC integration contact on your company's Procore account.
 
 - Requirements:
    
- Your company's Procore Administrator must submit a request to your company's Procore point of contact to enable this feature on the backend of Procore.
 - A user with 'Admin' permission on the project's Admin tool must enable the capability to create owner change orders as described in the steps below.
 
 - Additional Information:
    
- Not all ERP Integrations support the creation of owner change orders.
 
 
Steps
- Navigate to the project's Admin tool.
 - Under 'Project Settings', click General.
 - Scroll to 'Advanced'.
 - Mark the checkbox to Create Owner Change Orders.
 - Click Update.
 - Complete the steps in Export a PCCO to ERP.
 