Add Assets from Company Register
Background
You can select assets from the Company level Assets tool and assign them to your project to manage and track them for a specific project.
Things to Consider
-
Users are required to have Company Level permission to create assets to perform this action at the project level.
-
Attachments or related items are added to an asset at the company level, they will remain associated with the asset when it is added to a project.
-
When an asset is added to a project, parent and sub assets are also added to the same project to keep the hierarchy intact.
Prerequisites
Assets must be added in the Company level Assets tool:
Steps
-
Navigate to the project's Assets tool at the Project level.
-
Click on the Create and select Add from Company Register from the shortcut menu.
-
Select the assets you want to add to the project, then click Add.
-
Optional: Enter a note for context.
-
Click Add to add the asset to your project register.