Skip to main content
Procore

Commitments: Sliding Scale Retention Now Available in All Countries

This announcement represents a single point in time. Future releases may impact the information below.

Feature Announced: Wednesday, August 5, 2020Feature Released: Friday, August 7, 2020


 

Sliding Scale Retention Now Available in All Countries

Procore is pleased to announce an update to the project's Commitment tool. The update is the Sliding Scale Retention feature, which was initially released in January 2020 to Procore customers in Australia. It is now available to customers in all countries, including the United States and Canada. Users with 'Admin' permission on the project's Commitments tool have the ability to enable it on your Procore construction projects. For step-by-step instructions, see Enable Sliding Scale Retention Rules on a Commitment's Invoices.

What is included in this release?

After the feature is enabled, project users can use the new controls in the 'Advanced Settings' tab of a commitment to enable up to five (5) unique sliding scale rules on a purchase order or subcontract. Once saved, your settings will automatically adjust retention amounts on your project's subcontractor invoices.

add-a-rule-options.png

When configuring the retention settings on a commitment, you can choose to apply one (1) of these sliding scale options for each unique retention rule that you decide to add to a commitment: 

  • X% until Y% of original commitment value is held
    This rule lets you hold back X percent of of the original commitment amount until Y percent of the original commitment's value is held.  
  • X% until Y% Revised Commitment Value
    This rule lets you hold back X percent of the revised commitment amount until Y percent of the revised commitment's value is held. 
  • $ Amount is Held
    This rule lets you hold back X percent of a contract amount until a dollar amount that you specify is held.  

Once saved, Procore automatically applies your retention rules to each new invoice created for the commitment. It is recommended that you enable your settings before you begin invoicing,  as any changes to your rules can only be applied to new invoices. To learn more, see How do I enable the sliding scale feature in Procore?

Why is this important?

Procore users who choose to enable this can now automatically reduce retention on a commitment's invoices based on rules established in that commitment. This provides end users with these benefits from previous versions of Procore:

  • Provides an improved method to help owners and contractor's comply with contractual and regulatory retention requirements.
  • Eliminates the need to monitor retained values on individual invoices.
  • Eliminates the need to manually deduct retainage values in invoices. 

Common Questions

What is sliding scale retention?

Sliding scale retention refers to the portion of a contract amount due that is withheld from a contracted party (the party doing the work) by the contracting party (the party paying for the work).  The amounts withheld are based on a set of variable standards defined in the contract's scope of work. It is an industry-wide best practice in Australia, as well as legally regulated, to assure contractors and subcontractors meet all of the job's contractual obligations. 

Example: Applying Sliding Scale Retention in Procore

Although the terms of the retention on your construction project's contracts will vary from contract to contract, below is an example to show how sliding scale retention is designed to work:

  1. Let's assume you are a general contractor who has executed a $400,000.00 subcontract with a heavy equipment operator.
  2. During the course of the project, you plan to make progress payments to the subcontractor. Per your agreement, let's assume you have an industry-standard contract that obliges you to deduct 10% of the amount due on each subcontractor invoice until 5% ($20,000.00) of the original subcontract's value ($400,000.00) is held back.
  3. When 100% of the work on the subcontract's Schedule of Values (SOV) is complete, your agreement obliges you to release the first portion of the amount held back. In this example, you would want to release the first 2.5% ($10,000.00) of the original subcontract's original value ($400,000.00). 
  4. In six (6) or twelve (12) months after the first portion of the retention amount was released, your subcontract's terms require you to release the remaining 2.5% ($10,000.00) withheld from the subcontractor. 

back to common questions

How do I enable the sliding scale retention feature in Procore?

The default setting on your company's Procore account is OFF. After this feature is released, users with the appropriate permissions on the Commitments tool can immediately begin using it on your construction projects. For instructions, see  Enable Sliding Scale Retention Rules on a Commitment's Invoices.


back to common questions

Does sliding scale retention work with the default retainage settings in the Commitments tool?

No. When you save sliding scale retention rules on a commitment, those rules override all other retainage settings on the commitment. This includes the 'Enable Completed Work Retainage' or 'Enable Stored Material Retainage' settings under 'Invoice' on the Advanced Settings tab of a commitment. 


back to common questions

See Also

If you would like to ask questions or share any feedback, please contact support@procore.com.