View a Labor Budget to Actual Report (Android)
Objective
To view a labor budget to actual report on an Android mobile device.
Background
The Labor Budget to Actual Report compares the hours recorded in the Timesheets tool to the imported Budgeted Hours at a cost code level. The report is broken down by cost code and includes % of hours used, budgeted hours, job to date hours, and remaining hours.
Things to Consider
- Required User Permissions:
- 'Read Only' level permissions or higher on the project's Reports tool.
AND - 'Read Only' level permissions or higher on the project's Timesheets tool.
- 'Read Only' level permissions or higher on the project's Reports tool.
Prerequisites
Steps
- Navigate to the Timesheets tool on an Android mobile device.
- Tap the Reports icon.
- Tap the 'Hours' subtab.
This reveals the project's Labor Report (see image below).
- To return to the Timesheets tool, tap the X icon.