Background
The Weather section can be used to track many things. For example, you might want to track any delays to the project that may be due to weather conditions or compare team productivity against weather conditions. Each day also has a daily snapshot and weather report that automatically pulls weather information for the project's location from the weather software used on your project.
Steps
-
Navigate to the Daily Log tool using the Procore app on an Android mobile device.
-
Tap the date to select the calendar day for which you want to create a new entry.
-
Tap Weather.
4. Tap the Edit
icon.
5. Tap into the following fields to enter the relevant information:
-
Weather Delay: By default, the Weather Delay field will be set to No. Tap the button to indicate that there was a weather delay on the day you're recording data.
-
Sky: Tap the Sky field. Select from the menu an observation made of the sky that day. You may only select one observation.
-
Temperature: Tap the Temperature field. Select from the menu the approximate temperature on site that day.
-
Precipitation: Tap the Precipitation field. Enter the observed precipitation for the day.
-
Average: Tap the Average field. Enter the average temperature observed during the workday.
-
Wind: Tap the Wind field. Select from the menu the observed wind conditions.
-
Ground / Sea: Tap the Ground / Sea field. Select the status of the ground or sea around the project from the menu. You can only select information for either the ground or the sea.
-
Calamity: Tap the Calamity field. If the jobsite was subject to a calamity that day, enter the type by selecting from the following from the menu: earthquake, fire, flash flood, landslide, tornado, hurricane, snow, other.
-
Attachments: Tap on the following options to add photo, video, or file attachments to the entry:
-
Camera: Use your mobile device's camera to take a photo or video that is automatically added to the entry once you exit the camera.
-
Photos: Tap to select photos from your device's Gallery OR from Procore's Photos tool in the project.
-
Add from Procore
-
Tap Photos from Procore.
-
Tap the album that contains the photo(s) you want to include on the entry. OR Tap Create New Album to add a new photo album to the project. Note: You will need 'Standard' or 'Admin' permissions to the Daily Log tool to create an album.
-
Tap the photo(s) you want to attach.
-
Tap Done to attach it to the entry.
-
Add from Device
-
Files: Tap on a file from your mobile device to automatically attach it to the entry.
6. Tap Save.
Tip
-
Click Fix Errors to navigate to the first empty required field (if the required fields are empty or blank).
-
Click Next Field or Previous Field to view other empty fields. Once all required fields are filled, you are able to create or save the form.