About the Project Financials + MRI Platform X® Connector

Overview

With the Project Financials integration for the MRI Platform X® Connector, you can: 

  • Exchange information between systems to provide your project team with access to data from a single source-of-truth.
  • Reduce manual and duplicate data-entry to increase confidence that data is free from unnecessary errors.
  • Improve decision-making with access to the most up-to-date data available.
  • Streamline communication and information-sharing between your back-office and operational teams.

Feature Set Map


PROCORE
Exports data from Procore to MRI Platform X® Imports data from MRI Platform X® to Procore 
MRI Platform X®
COMPANIES   VENDORS
PROJECTS   JOBS

COST CODES
COST TYPES

 

COST CODES
DEFAULT CATEGORIES

BUDGETS 
ORIGINAL BUDGET
BUDGET MODIFICATIONS

  BUDGETS 
ORIGINAL BUDGETS
BUDGET REVISIONS
COMMITMENTS
COMMITMENT CONTRACTS & PURCHASE ORDERS
  CONTRACTS & PURCHASE ORDERS
COMMITMENT CHANGE ORDERS   CONTRACT CHANGE ORDERS
COMMITMENT INVOICES   CONTRACT DRAW
COMMITMENT PAYMENTS ISSUED   CONTRACT INVOICE PAYMENTS
DIRECT COSTS   JOURNAL ENTRIES
PAYABLES

Supported Versions

  • Required Software:
    • MRI Platform X® 5 or newer
  • Required Interface Plug-Ins:
    • Job Cost
    • Accounts Payable
    • General Ledger

Unsupported Features

  • The MRI Platform X® integration can only sync data on new jobs/projects. Any historical projects created before your company's ERP implementation cannot sync data.
  • Data from these Procore tools and items do NOT sync with MRI Platform X®
    • Prime Contracts 
    • Change Events
  • The following items in Procore will NOT integrate with MRI Platform X® .
    • Sub Jobs
      • The sub job feature is NOT supported with the Procore + MRI integration. All jobs from MRI Platform X® will equal exactly one Procore project, and sub jobs will not be enabled for those projects.
    • Project-Specific Cost Codes
      • Project-specific cost codes are NOT supported with the Procore + MRI Platform X® integration. Your company will have one (1) cost code list for use with all MRI Platform X®-integrated projects.
    • Tax Categories
      • Commitments, invoices and direct costs synced to or from MRI Platform X® will NOT evaluate tax information. 
    • Change Orders
      • No cost ($0) change orders are not supported in MRI.
      • Change orders made to Purchase Orders are not supported in MRI.
    • Retainage Release
      • Any retainage release will NOT happen automatically with the Procore + MRI Platform X® integration. Any Retainage Release will be ignored on invoices sent to MRI Platform X®, and that retainage must be released manually.
    • Materials Tracking
      • Materials presently stored and related retainage is NOT supported with the Procore + MRI Platform X® integration.
    • Multiple MRI Phases
      • The integration supports only one MRI Platform X® Phase per Procore Project 
    • Multiple MRI Entity IDs
      • The integration supports only one MRI Platform X® Entity ID per Procore Project

Common Questions

How often is data exchanged between Procore and MRI Platform X®?
Exports happen instantly upon approval by your organization’s Accounting User(s). Imports happen upon requests which can be made by your Project and Accounting Teams directly within Procore. 

Is MRI Platform X® Job Cost module required to integrate?
Yes. Procore requires the MRI Platform X® Job Cost module.

Will you be adding additional functionality?
We will continue to evaluate key functionality to include in the integration. What is listed in the above feature map simply denotes the current functionality.

See Also

MRI Platform X®: Setup Guide