Skip to main content
Procore

Integration by Ryvit: Send a CCO to ERP Integrations for Accounting Acceptance

 Objective

Background

Things to Consider

  • Required User Permission:
    • 'Admin' on the project's Commitments tool.
      AND
    • 'Admin' on the project's Change Orders tool.
      (Note: Typically, the project manager is responsible for sending an approved Commitment Change Order (CCO) to the ERP Integrations tool for acceptance by an accounting approver. See What is the accounting approver role?).
  • Minimum CCO Requirements:
    Before you can send a CCO in the Change Orders tool to the ERP Integrations tool, the CCO must satisfy these requirements:
    • ID Number. Must be 30 characters or less. 
    • Date Created: The date the CCO was created in Procore are exported to Viewpoint® Vista™ by default. This field cannot be edited. This corresponds to the 'Original Date' in Viewpoint® Vista™.
    • Title: Must be 60 characters or less. 
    • Description: This value in this field is exported from Procore into the 'Scope' field in Viewpoint® Vista™. Viewpoint® Vista™ imposes a one thousand (1000) character maximum on this field. Entries that exceed this maximum are truncated in Viewpoint® Vista™. The entire description will be stored in Procore.
    • Contract Company. Must be linked to a Viewpoint® Vista™ vendor. See Integration by Ryvit: Link Viewpoint® Vista™ Vendors and Procore Company Records
    • Status. Must be 'Approved.' 
    • Schedule of Values (SOV). Must include at least one (1) line item with a Integration by Ryvit Cost Code.
      Note: You can only add a line item to the commitment's SOV if its linked to an existing cost code and category.
  • Additional Information:
    • If desired, you can configure your default settings to use your Procore Change Order Number for an exported commitment's Viewpoint® Vista™ ID field. If enabled, the Viewpoint® Vista™ ID will auto-populate with the Procore Change Order Number. However, the value can still be edited. (Enabling this account-wide configuration setting requires 'Admin' level access on the ERP Integrations tool.)
  • Limitations:
    • Integration by Ryvit does not permit users to modify a contract line item on a CCO more than once.
    • If a contract line item on a CCO includes more than one (1) modification, Procore will automatically calculate the sum for all of that line item's modifications. After acceptance by an accounting approver, the amount of the items and send it to Viewpoint® Vista™ as a single (aggregated) value. 

Steps

See Also

The Integration by Ryvit is the product of a partnership between Procore and Ryvit, a third-party developer. Viewpoint, Inc. is not affiliated with this connector. All Viewpoint® Vista™ marks and logos are owned by Viewpoint, Inc.