Objective
To sync a Procore project with a Viewpoint® Spectrum® job.
Background
The are two methods for syncing projects and jobs:
- Integration by Procore: Add a Procore Project to Viewpoint® Spectrum®. You can create a new project in Procore and then export it to create a new job in Viewpoint® Spectrum® .
OR - Integration by Procore: Add a Viewpoint® Spectrum® Job to Procore. You can create a new job in Viewpoint® Spectrum® and then export it to create a new project in Procore.
Things to Consider
- Required User Permission:
- Limitations:
- You can only link new Viewpoint® Spectrum® jobs to new Procore projects (or new Procore projects to new jobs).
- You cannot link new or existing Viewpoint® Spectrum® jobs to existing Procore projects.
- You cannot link new or existing Procore projects to existing Viewpoint® Spectrum® jobs.
Demo
Workflows
Steps
There are two (2) ways to sync a Viewpoint® Spectrum® job with a Procore project. The steps to follow depend upon whether you create the job/project in Viewpoint® Spectrum® or Procore:
- If you want to create a new job in Viewpoint® Spectrum® and import into Procore, see Integration by Procore: Add a Viewpoint® Spectrum® Job to Procore.
AND - If you want to create a new Procore project and then export it into Viewpoint® Spectrum®, see Integration by Procore: Add a Procore Project to Viewpoint® Spectrum®.