Objective

To send a Prime Contract Change Order (PCCO) to the ERP Integrations tool for accounting acceptance.

Background

If you have a PCCO in Procore that does NOT exist in Viewpoint® Spectrum®, you can export it to Viewpoint® Spectrum®. The first step in this process is to locate the PCCO in the Project level Prime Contracts tool. Next, use the steps below to send it to the ERP Integrations tool. An accounting approver can then review the PCCO and accept or reject it. After it is accepted by the approver, the data is exported from Procore to Viewpoint® Spectrum®.

Things to Consider

  • Required User Permission:
    • 'Admin' permission on the project's Prime Contracts Tool. 
  • Prerequisites:
  • Requirements:
    • The Date field on a PCCO is required.
    • The Billing Item Code on a PCCO must be 10 characters or less.
    • The PCCO must be in the 'Approved' status.
    • For each associated line item that you add to the change order's Schedule of Values (SOV), you may designate a unique associated Prime Contract line item, or the same associated Prime Contract line item for all change order line items.  Note: The Associated Line Item is only visible and available when the ERP Integrations tool has been configured to work with Viewpoint® Spectrum® and the export prime contract change orders capability has been switched on in Procore by your Integration Implementation Specialist.

     

Steps

  1. Navigate to the project's Prime Contracts tool.
  2. Click the Change Orders tab.
  3. Locate the PCCO that you want to export the Prime Contract Change Orders list. 
  4. Choose from these options:
    • If the PCCO is in the Approved status, click View
      view-approved-erp-pcco.png
      OR
    • If the PCCO is in any other status, click Edit. Then change the status to Approved and click Save at the bottom on the page.
      Note: You must have 'Admin' permission on the Prime Contracts tool or be a 'Designated Approver' on the PCCO to change the status of a PCCO to Approved.
      edit-draft-erp-pcco.png
  5. If the PCCO is in the 'Approved' status, click Send to ERP.
    Note: If this button is grayed out and unavailable, check to see if the PCCO is in the 'Approved' status. Hover your mouse cursor over the tooltip for more information. 

    send-to-erp.png

    The system sends the PCCO to the Company level ERP Integrations tool and the icon at the top of the page changes to BLUE. See What do the ERP icons mean?
 Tip

If you send a PCCO to the ERP Integrations tool and discover you need to make changes to it, follow the steps below before an accounting approver accepts the PCCO for export to Viewpoint® Spectrum®: