Change Events in the Budget
Step | Description | Adds To | Removes From | Impact on Other Columns |
---|---|---|---|---|
1 | CE Created (ROM or RFQ Added) |
In Scope: No Change Out of Scope: 13 Approx COs |
N/A | 13 Approx PCOs + 15 Forecast to Complete + 16 Projected Cost at Completion + 17 Projected Over from Current + |
2A | PCO Created (Pending Status) |
In Scope: No Change Out of Scope: 14 Pending COs |
N/A | 14 Pending PCOs + 15 Forecast to Complete+ 16 Projected Cost at Completion + 17 Projected Over from Current + |
2B | CE Closed | In Scope: No Change Out of Scope: No Change |
In Scope: No Change Out of Scope: 13 Approx COs |
13 Approx PCOs - |
3 | PCO Approved | In Scope: No Change Out of Scope: 3 Approved COs |
In Scope: No Change Out of Scope: 14 Pending COs |
3 Approved COs + 4 Current Budget + 12 Cost to Complete + 14 Pending PCOs - 17 Projected Over from Current - |
4 | CCO Created (Pending Status) |
In Scope: N/A (PM Approves) Out of Scope: No Change |
N/A | N/A |
5 | CCO Approved (Approved or Out for Sig.) |
In Scope: 5 Subcontract Total Out of Scope: 3 Approved COs |
N/A | 8 Committed Cost + 10 Committed Cost to Complete + |