Change Events in the Budget

Step Description Adds To Removes From Impact on Other Columns
1 CE Created
(ROM or RFQ Added)
In Scope: No Change
Out of Scope: 13 Approx COs
N/A 13 Approx PCOs +
15 Forecast to Complete +
16 Projected Cost at Completion +
17 Projected Over from Current +
2A PCO Created
(Pending Status)
In Scope: No Change
Out of Scope: 14 Pending COs
N/A 14 Pending PCOs +
15 Forecast to Complete+
16 Projected Cost at Completion +
17 Projected Over from Current +
2B CE Closed In Scope: No Change
Out of Scope: No Change
In Scope: No Change
Out of Scope: 13 Approx COs
13 Approx PCOs -
3 PCO Approved In Scope: No Change
Out of Scope: 3 Approved COs
In Scope: No Change
Out of Scope: 14 Pending COs
3 Approved COs +
4 Current Budget +
12 Cost to Complete +
14 Pending PCOs -
17 Projected Over from Current -
4 CCO Created
(Pending Status)
In Scope: N/A (PM Approves)
Out of Scope: No Change
N/A N/A
5 CCO Approved
(Approved or Out for Sig.)
In Scope: 5 Subcontract Total
Out of Scope: 3 Approved COs
N/A 8 Committed Cost +
10 Committed Cost to Complete +