Koester Expectations - As Builts

Department: Quality Control 

Topic: Koester Expectations – As Builts 

 

Objective 

Documenting any changes throughout the project are important for project success for the owner long after the project is completed.  With Koester’s commitment to doing repeat business with owners that are good to work with, there is a good chance that we will be working on project that are being built now in the future. 

 

Things to Consider 

Marking up plans throughout the project is much easier than trying to recall info at the end of a project. 

Koester will collect As-Built Drawings from subcontractors, especially MEP subs.   

In certain situations using the MatterPort (3D scanning) might be beneficial 

 

Procedure  

Markups can be done on the Drawings tool in Procore.  See the Trainings on Drawings for more info. 

Items that should be marked up on drawings: 

  • Any RFI’s, ASI’s, Change Directives, verbal direction given by owners/architects 

  • Any deviations from contract documents, I.E. 

  • Room/wall dimensions that have been modified 

  • Pipes/ductwork/Electrical routing paths 

  • Items that routing isn’t shown on planset 

  • Electrical conduit/Mains 

  • Low voltage wiring 

  • Items that need to be located for maintenance/future remodels/additions 

  • Pipe locations/depths 

  • Cleanout/Valve/Junction Box Locations 

 

See Also:  