To view a schedule task using the Project level Schedule tool.
Start Date: The date that the task was scheduled to start on.
Finish Date: The date that the task is scheduled to finish on.
Actual Start Date: The actual start date for the task.
Start Variance: The difference between the baseline start date and the scheduled start date.
Baseline Start Date: The originally planned start date for the task.
Actual Finish Date: The actual finish date for the task.
Finish Variance: The difference between the baseline finish date and the scheduled finish date.
Baseline Finish Date: The originally planned finish date for the task.
Duration: The length of time scheduled for the task.
Percent Complete: The percentage of the task that is complete that was set in Microsoft Project, Primavera, or another integrated schedule software.
Note: When a new schedule is uploaded, the percent complete will be overwritten to match the native schedule file.
Task ID: The numerical value assigned to identify the task.
Critical Path: Displays whether or not the task has been set as "Critical Path" in Microsoft Project, Primavera, or another integrated schedule software.
Milestone: Displays whether or not the task has been set as "Milestone" in Microsoft Project, Primavera, or another integrated schedule software.
Note: Milestones can only be set through Microsoft Project, Primavera or another integrated schedule software; you can not set milestones in Procore.
Resources: Displays any resources affiliated with the task.
4. Request a Schedule Change for this Task: See Request a Schedule Change.
Scheduled Change Request History: Displays any change request history for the task. See Request a Schedule Change.
Scheduled Change History: Displays any changes made to the task by team members in Microsoft Project.
Note: The Microsoft Project add-in must be enabled to see change history.
Related Items: Displays any items related to the task set by the Schedule tool 'Admin' user.
Emails: View or compose emails related to the the schedule task.
Notes: This field will appear on a schedule tasks' view page on imported schedule files that include notes.
Note: This field is NOT available in all schedule software that integrates with with Procore.