Edit a Calendar Item

Objective

To edit a calendar item that was created in Procore.

Things to Consider

PROCORE SUPPORT: INTERNAL NOTES

If a customer using Primavera P6 asks about percent complete:

P6 has an attribute on activities called Percent Complete Type. This specifies which one of the three percent complete values (Duration, Physical, and Units) should be reported. Procore reads this setting and returns the specified percent complete type to Procore.

Steps

  1. Navigate to the project's Schedule tool. 
  2. Click the Calendar Item.
  3. Update the information.
  4. Click Save

See Also

 

If you would like to learn more about Procore's scheduling software and how it can help your business, please visit our construction scheduling software product page icon-external-link.png.