To configure advanced settings for the project's Budget tool.
Users with the appropriate permissions can configure a variety of advanced settings for the project's Budget tool.
This table details the settings under 'Budget Line Formatting' in the 'Budget Settings' page.
Setting | Element | Description |
---|---|---|
Display all values in red text on rows where any calculated column value is negative | Check box | Mark this check box to have all values in a line show as red when any column in the row is negative. |
This table details the settings under 'Forecasting' in the 'Budget Settings' page.
Setting | Element | Description |
---|---|---|
Autocalculate Forecast to Complete by Default | Check box | Mark the check box to automatically calculates the forecast to complete for new budget items. Procore does NOT retroactively calculate the 'Forecast to Complete' value on existing budget items. |
Enable Advanced Forecasting | Check box | Mark the check box to add the following features to Procore:
|
This table details the settings under 'Budget Changes' in the 'Budget Settings' page.
Setting | Description | |
---|---|---|
Require a Budget Change Adjustment to Change Event association | Yes/No |
YES: NO: |
Require Net Zero Budget Change Amounts | Check box |
Mark the check box to require net zero budget change amounts when creating budget changes. This requires the user creating the budget change to move the full amount of an adjustment to another line item before allowing them to click Save. See Create Budget Changes. |
Allow Budget Changes to be Billed on Owner Invoices |
Check box | Mark this check box to allow users to add newly approved budget changes to the most recent owner invoice: Note: Selected budget changes must have a net zero balance. |
This setting is only available to Procore customers who have not completed migration to the budget changes feature. See About Budget Changes and Migrating to Budget Changes from Budget Modifications.
Setting | Description | |
---|---|---|
Allow Budget Modifications Which Modify Grand Total | Check box |
Mark the check box to turn this setting ON to:
|
Instead of the steps below, Procore recommends that you set user access permissions to your project tools using a permission template. See Manage Project Permissions Templates.
The color-coded icons in the user permissions area denotes the user's access permission level to the tool. To learn more, see What are the default permission levels in Procore?
Icon | Color | Definition |
---|---|---|
GREEN | The user has been granted this access permission level to the tool. | |
RED | The user has NOT been granted this access permission to the tool. | |
GREY | The user is either a Procore Administrator or has been granted permissions to the Procore tools on this project using a permissions template (see What is a permissions template?). To change the user's permission level to this tool, see Manage Project Permissions Templates. |