Configure Flat Rate Columns
- Last updated
- Save as PDF
In Beta
Company Administrators can enable the Resource Management: Rate Tables - Company & Project Rate Management beta in Procore Explore. (US 2 | UK)Background
To build a rate table, you must first define its columns. Rate columns categorize your rates by type (labor or equipment) and financial purpose: cost rates represent the internal expense incurred by using a resource, while billable rates represent the amount charged to a client.
Additionally, the Allow Project Overrides setting controls flexibility. If enabled, projects can customize the rates assigned from the company level. If disabled, projects must use the rates as-is. Typically, you will keep overrides disabled for fixed internal costs, but enable them for billable rates so projects can adjust pricing to match specific client contracts.
Things to Consider
-
After you create a rate, the Resource Category cannot be edited.
-
Columns cannot be deleted. However, they can be edited and repurposed.
Steps
-
Navigate to the company's Rates tool.
-
Click the configure settings
icon. -
Click Create and select Flat Rate.
-
Enter the flat rate column information.
Show/Hide Fields
-
Name. The name of the column.
-
Rate Category. Whether the rate is a cost or billable rate.
-
Resource Category. Whether the rate is applied to equipment or labor.
-
Unit of Measure. The unit of measure applied to the rate.
-
Description. A description of the rate.
-
-
Set Overrides and Privacy.
-
Allow Project Overrides. Mark the checkbox to allow project rate admins to override the value for their specific project.
-
-
Save the column.
-
Click Save to save changes made to the column.
-
Click Save as New Column to create a new column.
Tip
To edit columns, select the column and update the information. Then click Save.
-