Background
After you create your rate tables, you can assign them to projects.
Things to Consider
-
Currently, you can assign multiple equipment or labor rate tables to a project, but their effective date ranges must not overlap. Only one equipment table and one labor table can be active at any given time.
Steps
-
Navigate to the company's Rates tool.
-
Select the rate table.
-
From the Rate Tables list, locate the rate table. Then, click the projects hyperlink in the 'Assigned Projects' column.
-
Click the rate table. Under 'Assigned Projects', click the projects hyperlink.
-
-
Mark the checkboxes for the projects you want to assign the table to.
-
Click Assign to confirm.