Microsoft Project Detailed Data Mapping

 Note
The below fields are supported in Procore. Additional or custom fields added in Microsoft Project will not sync to Procore.

Gantt View

In Procore, the Gantt chart reads directly from the Microsoft Project schedule file. The chart below shows how each field maps from Microsoft Project to Procore. You can find the Gantt view in the Gantt section of the Project Schedule tool. See View a Gantt Schedule.


PROCORE Field Name
Imports data from Microsoft Project to Procore
Microsoft Project Field Name
ID tri-left-arrow-green.png ID
Task Name tri-left-arrow-green.png Task Name
Baseline Start1 tri-left-arrow-green.png Baseline Start1
Baseline Finish1 tri-left-arrow-green.png Baseline Finish1
Start2 tri-left-arrow-green.png Start
Finish2 tri-left-arrow-green.png Finish
Duration tri-left-arrow-green.png Duration
% Complete tri-left-arrow-green.png % Complete, Physical % Complete, Work % Complete 3,4
Predecessors tri-left-arrow-green.png Predecessors
Successors tri-left-arrow-green.png Successors
Notes tri-left-arrow-green.png Notes
WBS (Work Breakdown Structure) tri-left-arrow-green.png WBS (Work Breakdown Structure)
Resources tri-left-arrow-green.png Resource Names

 

Only one Baseline Start and Baseline Finish is supported in Procore.

2 If the Start and Finish dates are blank on the schedule file, the Procore fields will inherit the dates referenced in the Microsoft Project file in the Project Information Section.

The schedule tool will show the highest values of the three based on these percent complete readings: % complete, physical % percent, or work % complete.

4 The schedule tool only displays the change history for % complete and does not display a change history for physical % complete or work % complete.

Schedule Task Details

The Schedule Task Details page gives a detailed look at an individual schedule task and provides details such as start and finish variance, as well as requesting a schedule change. See Request a Schedule Change and View a Schedule Task.


PROCORE Field Name
Imports data from Microsoft Project to Procore
Microsoft Project Field Name
Task ID tri-left-arrow-green.png ID
Task Name tri-left-arrow-green.png Task Name
Baseline Start1 tri-left-arrow-green.png Baseline Start1
Baseline Finish1 tri-left-arrow-green.png Baseline Finish1
Start tri-left-arrow-green.png Start
Finish tri-left-arrow-green.png Finish
Duration tri-left-arrow-green.png Duration
% Complete tri-left-arrow-green.png % Complete, Physical % Complete, Work % Complete 2,3
WBS (Work Breakdown Structure) tri-left-arrow-green.png WBS (Work Breakdown Structure)
Resource tri-left-arrow-green.png Resource Names
Actual Start tri-left-arrow-green.png Actual Start
Actual Finish tri-left-arrow-green.png Actual Finish
Start Variance tri-left-arrow-green.png Start Variance
Finish Variance tri-left-arrow-green.png Finish Variance
Critical Path3 tri-left-arrow-green.png Critical Path4

 

Only one Baseline Start and Baseline Finish is supported in Procore.

2 The schedule tool displays % complete, but does not display physical % complete or work % complete.

3 The schedule tool only displays the change history for % complete and does not display a change history for physical % complete or work % complete.

The critical path fields reads as Yes or No.

 

Lookaheads

Lookaheads allows users to create schedule subtasks based off their integrated Microsoft Project schedule file. Lookaheads operates separate from the integrated schedule file and modifications to a Lookahead do NOT impact the integrated schedule. Lookaheads can be created to range from 1-6 weeks. See Create a Lookahead Schedule.


PROCORE Field Name
Imports data from Microsoft Project to Procore
Microsoft Project Field Name
ID tri-left-arrow-green.png ID
Start tri-left-arrow-green.png Start
Finish tri-left-arrow-green.png Finish
Notes   Notes
Resource tri-left-arrow-green.png Resource Names
Company   Company
Assignee   Assignee
Task Name tri-left-arrow-green.png Task Name
Activity ID   N/A

Note: Blank import fields indicate the the field does not map to Procore.