Send a Budget to ERP Integrations for Accounting Acceptance

Objective

To send a Procore project's budget to the ERP Integrations tool for acceptance by an accounting approver.

Background

After creating a project budget and reviewing its contents to ensure your original budget is final, a budget is locked (see Lock a Budget). At this point, a user with the appropriate permission on the Budget tool can use the steps below to send the budget to the ERP Integrations tool where it can be reviewed and approved for export to the integrated ERP system

Things to Consider

Steps

  1. Navigate to the project's Budget tool. 
  2. In the Budget page, under Cost Code Detail, review the budget's line items. 
    Note: If your budget contains sub job information, it is listed in the budget. 
  3. When you are ready to send your budget to the ERP Integrations tool for acceptance by an accounting approver, click Send to ERP (or, if you've previously sent the budget, click Re-send to ERP).

    send-to-erp.png

    Notes:

    • If the Send to ERP (or Re-send to ERP) button is grayed out and unavailable, hover your cursor over the question mark (?) to learn why. Typically, it's because the project's ERP data has not yet been synced or because the item does not meet the minimum requirements (see above). 
    • If the Retrieve from ERP button appears, the data has already been sent to the ERP Integrations tool. 
  4.  After you sync the budget for the first time, you can also sync an updated Procore budget to QuickBooks:

The system sends the original budget and budget modifications to the ERP Integrations tool where it can be accepted or rejected for export to QuickBooks by an accounting approver.

Next Steps

See Also