Unlink CCOs Synced with Sage 300 CRE®

Objective

To sever the connection between a Commitment Change Order (CCO) that has been synced between Procore and Sage 300 CRE®.

Background

When a Procore project's CCOs are synced with Sage 300 CRE®, a link is created between the records stored in each system. Sometimes, users will inadvertently export a CCO from Procore and then discover that the CCOs data was entered incorrectly. When this occurs, the record first needs to be deleted in Sage 300 CRE®. Next, use the steps below to unlink the record. You can then re-enter the correct information so it can be exported to Sage 300 CRE®.

 Note

To sever the connection between a CCO in Procore and Sage 300 CRE®, always complete these steps in the order specified:

  1. Delete the CCO in Sage 300 CRE®. See your Sage 300 CRE® documentation for steps.
  2. Continue with the Steps below. 

Things to Consider

Prerequisites

Steps

  1. Navigate to the company's ERP Integrations tool.
  2. Click Commitment Change Orders
  3. Locate the desired CCO under Change Orders - Sucessfully Synced with Sage 300 CRE®.
  4. Click Unlink.
    • If the unlink action is successful, the 'Successful Unlinked' message appears in GREEN.
    • If the unlink action is not successful, the "The CCO is still in Sage 300 CRE®. Please delete it before retrying" message appears in RED. 