Model Standards with Procore Model Tool
- Last updated
-
-
Save as PDF
-
- Work in a single model
- Always create a KAST Shell Revit and NWF files
- Import design files into KAST Shell Revit model
- Export NWC for each discipline from KAST Shell
- Create KAST Shell NWF from exported NWCs
- Publish this NWF to Procore
- Model status on Procore
- "For Coordination" until whole building signed off
- "For Construction" once entire building signed off
- Have saved viewpoints for every level of Coordination
- Put Saved Views in viewpoint folder named "Procore" for any views we want to export to Procore
- Default view should be Bldg Ext w Status Boxes
- Should be one Clean ext view with no status boxes
- Create a saved view for (at minimum) each unique floor
- L[XX] - [DESCRIPTION] - [STATUS] - [EXCEPTIONS/INCLUSIONS (if any)]
- [STATUS]
- In-Progress
- For-Construction
- Not Started
- Always use "In Progress" unless signoff email has been sent for some or all of the floor
- e.g.
- L00 - UG - In Progress
- L10 - Units - Final
- L05 - Amenity & Units - Final Units Only"
- Published Model
- 3D box indicating all floors for coordination (in Shell Model)
- Red for floors not yet started
- Yellow for floors in-progress
- Orange for floors partially signed-off
- Green for floors signed-off
- ALWAYS publish grids to enable 2D views in mobile
- this enables the project teams to click on walls and floors to get dimensioned 2D views of those elements
- if you don't see this grid icon on the model in mobile...

- ...then the team won't be able to do this in the field (note "2D View" next to "Section")